Disclaimer By attending the presentation or by reading the presentation slides you agree to be bound as follows: This Presentation is prepared by Juniper Green Energy Limited(“Company”) and is for information purposes only without regards to specific objectives, financial situations or needs of any particular person and is not and nothing in it shall be construed as an invitation, offer, solicitation, recommendation or advertisement in respect of the purchase or sale of any securities of the Company or any affiliates in any jurisdiction or as an inducement to enter into investment activity and no part of it shall form the basis of or be relied upon in connection with any contract or commitment or investment decision. This Presentation does not take into account, nor does it provide any tax, legal or investment advice or opinion regarding the specific investment objectives or financial situation of any person. This Presentation and its contents are confidential and proprietary to the Company and/or its affiliates and no part of it or its subject matter be used, reproduced, copied, distributed, shared, or disseminated, directly or indirectly, to any other person or published in whole or in part for any purpose, in any manner whatsoever. The information contained in this Presentation is a general background information of the Company and its affiliates. Wedon’t assume responsibility to publicly amend, modify or revise any information contained in this Presentation on the basis of any subsequent development, information or events, or otherwise. This Presentation should not be considered as a recommendation to any investor to subscribe to any security. This Presentation may include certain statements that are, or may be deemed to be,“forward-lookingstatements” and relate to the Company, its affiliates and its financial position, business strategy, events and courses of action. Forward-looking statements and financial projections are based on the opinions and estimates of management at the date the statements are made and are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those anticipated in the forward-looking statements and financial projections. Forward-looking statements and financial projections include, among other things, statements about: our expectations regarding our expenses, sales and operations; our future customer concentration; our anticipated cash needs, our estimates regarding our capital requirements, our need for additional financing; our ability to anticipate the future needs of our customers; our plans for future products and enhancements of existing products; our future growth strategy and growth rate; our future intellectual property; and our anticipated trends and challenges in the markets in which we operate. Forward-looking statements are not guarantees of future performance including those relating to general business plans and strategy, future outlook and growth prospects, and future developments in its businesses and its competitive and regulatory environment. No representation, warranty or undertaking, express or implied, is made or assurance given that such statements, views, projections or forecasts in the Presentation, if any, are correct or that any objectives specified herein will be achieved. We, or any of our affiliates, shareholders, directors, employees, or advisors, as such, make no representations or warranties, express or implied, as to, and do not accept any responsibility or liability with respect to, the fairness, accuracy, completeness or correctness of any information or opinions contained herein and accept no liability whatsoever for any loss, howsoever, arising from any use or reliance on this Presentation or its contents or otherwise arising in connection therewith. The information contained herein is subject to change without any obligation to notify any person of such revisions or change and past performance is not indicative of future results. It is clarified that this Presentation is not intended to be a document or advertisement offering for subscription or sale of any securities or inviting offers or invitations to offer or solicitation to offer from the public (including any section thereof) or any class of investors. This document has not been and will not be reviewed or approved by a regulatory authority in India or by any stock exchange in India. No rights or obligations of any nature are created or shall be deemed to be created by the contents of this Presentation. 2
Page 3
Agenda 01 Business & Operational Highlights 02 Financial Highlights 03 Capacity Execution and Growth Plan 04 Project Details 05 Annexure 3
Page 4
Key Highlights – Q2 FY27 ✓ Operational capacity of the company reached to 2,844 MWp + 604 MWh BESS as on date ✓ Commissioned 1,036 MWp RE capacity & 503 MWh BESS in FY27 till date across 11 sites in 3 states ✓ Commissioned 316 MWp of RE capacity and ~100 MWh of BESS in Q2 FY27, in line with the guidance of 250–300 MWp for the quarter ✓ Operational wind capacity increased by 542 MW from 151 MW in FY26 to 693 MW; wind CUF of 50% in Q2 FY27 ✓ Generation up 127% YoY to 1,130 Mn units in Q2 FY27 ✓ H1 FY27 portfolio update: PPA signed for 50 MW (SJVN FDRE) and LoAs received for 280 MW contracted capacity (SECI FDRE RTC 230 MW; GUVNL wind 50 MW), taking total operational + PPA signed capacity to 6,139 MWp and total portfolio to 11,218 MWp + 8,989 MWh BESS ✓ Commissioned 51 units of India’s largest wind turbine by rotor diameter (5 MW, 181 m rotor) in FY27 till date 4 SOLAR CAPACITY (MWp) 1,657 2,151 FY26 As on date WIND CAPACITY (MW) 151 693 FY26 As on date BESS CAPACITY (MWh) 101 604 FY26 As on date TOTAL RE + BESS CAPACITY 1,808 2,844 FY26 As on date RE (MWp) BESS (MWh) 101 604 2,844 MWp + 604 MWh +494 MWp +542 MW +503 MWh+1,036 MWp 503 MWh
Page 5
Key Highlights – Q2 FY27 ✓ EBITDA margin expanded to 91% in Q2 FY27 from 81% in Q2 FY26 ✓ Credit rating of JGEL upgraded to AA- (Stable) / A1+ by ICRA from A+ (Positive) / A1 ✓ Strengthening SPV credit profile: 7 upgrades and 2 new ratings across 9 SPVs in FY27, with 3 SPVs now in the AA category 5 Q2 FY27 Financial Performance Snapshot TOTAL INCOME1 (INR Cr) 160 372 Q2 FY26 Q2 FY27 EBITDA (INR Cr) 130 340 Q2 FY26 Q2 FY27 PAT2 (INR Cr) (18) 54 Q2 FY26 Q2 FY27 CASH PAT3 (INR Cr) 40 153 Q2 FY26 Q2 FY27 1 Total income includes other income 2 Adjusted for one-time expenses of INR 22.97 Cr on account of refinancing and IPO 3 Cash PAT = PAT + Depreciation + one-time expenses of INR 22.97 Cr on account of refinancing and IPO 2.3x YoY 2.6x YoY Turnaround 3.9x YoY
Page 6
S E C T I O N 01 Business & Operational Highlights Image source: Juniper project asset
Page 7
Business Highlights – H1 FY27 ✓ Commissioned 917 MWp (Solar: 494 MWp, Wind: 423 MW) in H1 FY27 ✓ Further commissioned 119 MW Wind capacity post September 30, 2026, taking total operational capacity as on date to 2,844 MWp ✓ Commissioned ~503 MWh BESS in H1 FY27. ✓ Target BESS Installation of~4,500 MWh by June 2027 & ~10,000 MWh by March 2028 6 7 Operational Capacity 2,844 MWp (As on Date) Operational BESS Capacity 604 MWh Total Portfolio as on Date 11,218 MWp + 8,989 MWh BESS ✓ PPA signed with SJVN for 50 MW under FDRE portfolio at a tariff of INR 4.25/kWh ✓ LoA received from SECI for FDRE Round-the-Clock (Thermal Mimic)– 230 MW contracted (planned 870 MWp + 2,200 MWh BESS) at INR 5.26/kWh ✓ LoA received for 50 MW wind project from GUVNL at a tariff of INR 3.51/kWh ✓ Commissioned India's first FDRE project under the SJVN FDRE scheme tender
Page 8
Operational Highlights – H1 FY27 Operational Highlights 1CUF is calculated on AC capacity from the next month in which the project is fully commissioned 2Impact of curtailment of power is not considered for the purpose of calculation of grid availability 8 GENERATION (Mn Units) 1,046 2,075 H1 FY26 H1 FY27 TOTAL CUF¹ (%) 24.1% 28.5% H1 FY26 H1 FY27 WIND CUF¹ (%) 41.3% 50.0% H1 FY26 H1 FY27 AVAILABILITY (%) Plant Availability 99.1% H1 FY26 98.7% H1 FY27 Grid Availability² 99.4% H1 FY26 99.5% H1 FY27 ✓ Generation increased 98% YoY to 2,075 Mn units, driven by capacity additions & strong wind performance ✓ Juniper Green Beam (50.4 MW wind) delivered a CUF1 of 58.3% in H1 FY27 & Juniper Green Kite (72.45 MW wind) delivered a CUF1 of 57.9% in H1 FY27. +98% YoY +440 bps YoY +870 bps YoY
Page 9
Other Business Highlights – Q2 FY27 Connectivity 6 ✓ Connectivity available (including granted and/or applied) for full portfolio ✓ Surplus Connectivity of more than 5,200 MW available for the future bids (including granted and/or applied) ✓ Connectivity available for installation of more than 20,000 MWh of BESS (including granted and/or applied) Land ✓ Over 16,000 acres of land available for the Under Construction Contracted and Awarded projects ✓ More than 100 locations available for Wind Turbine Installation for Under Construction Contracted and Awarded projects Execution capabilities ✓ Commissioned 1,036 MWp & 503 MWh BESS till date in FY27 across 11 sites in 3 states ✓ In-house EPC team enables end-to-end, parallel execution across multiple sites in various states, at both STU and CTU levels SPV State/CT U Type MWp BESS MWh Juniper Green Stellar Pvt. Ltd. CTU FDRE 344 201 Juniper Green Stellar Pvt. Ltd. - GS CTU FDRE 178 201 Juniper Green Beam & Kite Pvt. Ltd. GJ-STU Wind 41 - Juniper Green Spark Four Pvt. Ltd. GJ-STU Hybrid 82 - Juniper Green Energy Limited GJ-STU Hybrid 190 - Juniper Green Beam Eight Pvt. Ltd. MH-Tata Power Hybrid 86 - Juniper Green Spark Ten Pvt. Ltd. MH-STU Hybrid 25 - Juniper Green Kite Pvt. Ltd. GJ-STU Wind 90 - Juniper Green Cosmic Pvt. Ltd. CTU BESS - 100 Total 1,036 503 Capacity addition till date – FY27 9
Page 10
S E C T I O N 02 Financial Highlights Image source: Juniper project asset
Page 11
Financial Highlights – Q2 TOTAL INCOME ₹372 Cr ▲ 2.3x YoY | Q2 FY26: ₹160 Cr ▲ 1.15x QoQ | Q1 FY27: ₹324 Cr EBITDA ₹340 Cr ▲ 2.6x YoY | Q2 FY26: ₹130 Cr ▲ 1.15x QoQ | Q1 FY27: ₹294 Cr EBITDA MARGIN 91% ▲ +1,034 bps YoY | Q2 FY26: 81% ▲ +53 bps QoQ | Q1 FY27: 91% OPERATING INCOME ₹345 Cr ▲ 2.4x YoY | Q2 FY26: ₹146 Cr ▲ 1.2x QoQ | Q1 FY27: ₹291 Cr OPERATING EBITDA ₹313 Cr ▲ 2.7x YoY | Q2 FY26: ₹116 Cr ▲ 1.2x QoQ | Q1 FY27: ₹261 Cr OPERATING EBITDA MARGIN 91% ▲ +1,152 bps YoY | Q2 FY26: 79% ▲ +90 bps QoQ | Q1 FY27: 90% PAT1 ₹54 Cr ▲ Turnaround YoY | Q2 FY26: ₹(18) Cr ▲ 1.02x QoQ | Q1 FY27: ₹53 Cr3 CASH PAT 2 ₹153 Cr ▲ 3.9x YoY | Q2 FY26: ₹40 Cr ▲ 1.2x QoQ | Q1 FY27: ₹127 Cr3 1Adjusted for one-time expenses on account of refinancing and IPO: INR 22.97 Cr in Q2 FY27 2Cash PAT = PAT + Depreciation + one-time expenses on account of refinancing and IPO: INR 22.97 Cr in Q2 FY27 3Adjusted for one-time expenses on account of refinancing : INR 19.29 Cr in Q1 FY27 11
Page 12
Financial Highlights – H1 TOTAL INCOME ₹696 Cr ▲ 2.0x YoY | H1 FY26: ₹341 Cr EBITDA ₹634 Cr ▲ 2.2x YoY | H1 FY26: ₹288 Cr EBITDA MARGIN 91% ▲ +666 bps YoY | H1 FY26: 84% OPERATING INCOME ₹636 Cr ▲ 2.1x YoY | H1 FY26: ₹307 Cr OPERATING EBITDA ₹574 Cr ▲ 2.3x YoY | H1 FY26: ₹254 Cr OPERATING EBITDA MARGIN 90% ▲ +760 bps YoY | H1 FY26: 83% PAT1 ₹106 Cr ▲ 32.4x YoY | H1 FY26: ₹3 Cr CASH PAT 2 ₹280 Cr ▲ 2.5x YoY | H1 FY26: ₹111 Cr 1Adjusted for one-time expenses of INR 42.26 Cr in H1 FY27 on account of refinancing and IPO 2Cash PAT = PAT + Depreciation +one-time expenses of INR 42.26 Cr in H1 FY27 on account of refinancing and IPO 12
Page 13
Capex and Debt Details ✓ Capex of INR 2,591 Cr incurred during Q2FY27 ✓ Total Gross block of INR 12,249 Cr as on September 30, 2026 ✓ Total CWIP of INR 6,646 Cr as on September 30, 2026 including capital advances ✓ Total Debt of INR 13,711 Cr outstanding as on September 30, 2026 ✓ ~68% of project borrowings from Financial institutions (PFC, IREDA, NaBFID, IIFCL), whose annually reset rates track their own long-term cost of funds – limiting interest rate volatility ✓ Refinanced more than INR 2,550 Cr at wt. avg. interest rate of less than 8% p.a. across 5 projects in the current Fiscal ✓ Weighted average cost of debt for the operational portfolio stands at 8.46% p.a. ✓ Net Debt / Net Worth as on September 30, 2026 stands at 2.22x ✓Primary funds of INR 1,800 Cr raised through IPO in August’26 ✓ Post IPO, Net worth increased by 51% QoQ to INR 5,216 Cr 6 Total Capex INR 18,895 Cr (As on September 30, 2026) Net Debt INR 11,607 Cr (As on September 30, 2026) Net Worth INR 5,216 Cr (As on September 30, 2026) 13
Page 14
Off-taker Credit Quality Off-taker Category MWp Rating Share SJVN Central 2,641 CARE AA+ 24% NHPC Central 2,444 CARE AAA 22% NTPC Central 1,740 ICRA AAA 16% SECI Central 1,571 ICRA AAA 14% Central off-taker – Sub total A 8,395 75% GUVNL State 1,262 CARE AA+ 11% MSEDCL State 1,073 Acuite A Stable 10% Tata Power Company Ltd. Private 278 CRISIL AA+ 2% State & Private off-taker – Sub total B 2,613 23% Merchant Merchant 210 – 2% Total portfolio 11,218 100% 98% Of portfolio is with off-takers rated “A” or above 98% of portfolio secured through long-term PPAs (typically 25 years) Off-taker mix (MWp) 24% 22% 16% 14% 11% 10% 2% 2% Central-SJVN (CARE AA+ Stable) Central-NHPC (CARE AAA Stable) Central-NTPC (ICRA AAA Stable) Central-SECI (ICRA AAA Stable) GUVNL (CARE AA+ Stable) MSEDCL (Acuite A Stable) TPCL (CRISIL AA+ Stable) Merchant 11,218 MWp 14 Days Receivable Outstanding (Days)1 23 17 22 25 FY24 FY25 FY26 H1 FY27 1DRO is calculated as closing trade receivables (excluding unbilled revenue) divided by billed revenue (revenue from operations plus opening unbilled revenue minus closing unbilled revenue), multiplied by the number of days for the period.
Page 15
S E C T I O N 03 Capacity Execution and Growth Plan Image source: Juniper project asset
Page 16
Total Portfolio Breakup Capacity As on date Contracted (MW) AC (MW) DC (MWp) BESS (MWh) Solar 935 935 1,322 201 Wind 279 282 282 - WSH 426 471 595 - FDRE 251 531 645 403 Operational - A 1,891 2,219 2,844 604 Wind 150 150 150 - WSH 524 601 767 - FDRE 1,039 1,730 2,378 3,485 Under Construction – Contracted - B 1,714 2,481 3,294 3,485 Sub-Total (A+B) 3,604 4,700 6,139 4,089 Wind 50 50 50 - Hybrid 1,650 1,980 2,572 - FDRE 880 1,680 2,458 4,900 Under Construction – Awarded - C 2,580 3,710 5,079 4,900 Grand Total (A+B+C) 6,184 8,410 11,218 8,989 Portfolio Stage Mix (MWp) 2,844 3,294 5,079 11,218 Operational + PPA Signed + LOA Received* Total Portfolio 604 MWh + 3,485 MWh + 4,900 MWh + 8,989 MWh + ✓ 84% of the total portfolio consists of FDRE & WSH projects ✓ Wt. avg tariff of the total portfolio is INR 3.70 /kWh 16
Page 17
Status of Under-Construction Contracted Projects Entity Type DC (MWp) BESS (MWh) Substation Name GNA Timelines Expected COD/Plant Readiness BESS installation date Juniper Green Spark Four Private Limited WSH 70 - Faredi, Choraniya & Charadva Operational Nov’26 - Juniper Green ETA Five Private Limited WSH 135 - Tuljapur Operational Nov-Dec’26 - Juniper Green Power Five Private Limited WSH 26 - Tuljapur Operational Dec’26 - Juniper Green Stellar Private Limited FDRE 83 - F4S1 & JK-1A Nov’26 Dec'26 - Juniper Green Stellar Private Limited- GS FDRE 55 - F4S1 & JK-1A Nov’26 Dec'26 - Juniper Green Sigma Eight Private Limited FDRE 192 281 Rajur & Chapalgaon Operational Mar’27 Mar'27 Juniper Green Beta Private Limited WSH 298 - Bhadla-III & JK-1A Mar’27 Mar’27 - Juniper Green Beta Private Limited WSH 237 - Bhadla-III, F4S1 & JK-1A Mar’27 Mar'27 - Juniper Green Light Ten Private Limited FDRE 480 884 F4S2 Jun’27 Jun'27 Phased commissioning Apr’27 onwards Juniper Green Beta Six Private Limited FDRE 500 784 Barmer-1 Jun’27 Jun'27 Jun'27 Juniper Green Bess Zeta Private Limited FDRE 451 362 F4S2 & Barmer-1 Jun’27 Jun'27 Phased commissioning Apr’27 onwards Juniper Green Bess Two Private Limited Wind 100 - Mansar & Bhalgamda Operational Jul’27 - Juniper Green Cosmic Private Limited FDRE 500 938 F4S2 , Bikaner-III & Bikaner-II Sep’27 Sep'27 Phased commissioning Oct’26 onwards Juniper Green Bess Delta Private Limited Wind 50 - Ghiyawad & Bhogat Operational Nov’27 - Juniper Nirjara Energy Private Limited FDRE 116 235 Bikaner-II Sep’27 Dec’27 Dec’26 Total – UCC 3,294 3,485 17
Page 18
S E C T I O N 04 Project Details Image source: Juniper project asset
Page 19
Project Wise Portfolio Breakup – Operational Entity Type Off-taker AC (MW) DC (MWp) BESS (MWh) Tariff (Rs./ kWh) COD Nisagra Renewable Energy Private Limited + Juniper Green Energy Limited Solar MSEDCL 100 144 - 3.38 Dec’19-Mar’20 Juniper Green Sigma Limited Solar GUVNL 120 175 - 2.83 Oct–Dec’20 Juniper Green Three Private Limited Solar GUVNL 190 262 - 2.75 Mar’22 Juniper Green Field Private Limited Solar MSEDCL 150 207 - 3.06 Jun–Aug’22 Juniper Green Gamma One Private Limited Solar MSEDCL 75 105 - 2.90 Mar’24 Juniper Green Cosmic Private Limited Solar + BESS Merchant 100 140 201 Merchant Oct’24 & Jan’26 Juniper Nirjara Energy Private Limited Solar Merchant 50 70 - Merchant Mar’25 Juniper Green Ray Two Private Limited Solar MSEDCL 150 217 - 2.75 May–Jun’25 Juniper Green Beam Private Limited Wind GUVNL 69 69 - 2.90 Mar–Jun’24 Juniper Green Beam Private Limited Wind GUVNL 50 50 - 2.95 Jul’25–May’26 Juniper Green Kite Private Limited Wind GUVNL 72 72 - 3.11 Oct’25–May’26 Juniper Green Kite Private Limited Wind GUVNL 90 90 - 3.44 Jun-Jul’26 Juniper Green Spark Ten Private Limited WSH MSEDCL 100 134 - 3.60 Oct’25–Sep’26 Juniper Green Energy Limited WSH GUVNL 150 190 - 3.04 Apr–Oct’26 Juniper Green Beam Eight Private Limited WSH Tata Power 75 86 - 3.27 Jul–Sep’26 Juniper Green Power Five Private Limited (partial) WSH MSEDCL 75 103 - 3.60 Jun–Jul’25 Juniper Green Spark Four Private Limited (partial) WSH GUVNL 70 82 - 3.30 May-Sep’26 Juniper Green Stellar Private Limited (partial) FDRE SJVN 393 467 201 4.38 Mar–Oct’26 Juniper Green Stellar Private Limited - Greenshoe (partial) FDRE SJVN 138 178 201 4.38 Apr-Aug’26 Total – Operational 2,219 2,844 604 19
Page 20
PPA Signed – Under Construction Entity Type Off-taker AC (MW) DC (MWp) BESS (MWh) Tariff (₹/kWh) Tariff Adoption Status Connectivity Status Juniper Green Beta Private Limited WSH NTPC 238 298 - 3.36 Adopted Secured Juniper Green Spark Four Private Limited WSH GUVNL 50 70 - 3.30 Adopted Secured Juniper Green Power Five Private Limited WSH MSEDCL 26 26 - 3.60 Adopted Secured Juniper Green ETA Five Private Limited WSH MSEDCL 101 135 - 3.60 Adopted Secured Juniper Green Stellar Private Limited FDRE SJVN 83 83 - 4.38 Adopted Secured Juniper Green Stellar Private Limited - GS FDRE SJVN 55 55 - 4.38 Adopted Secured Juniper Green Beta Private Limited WSH SECI 185 237 - 3.21 Adopted Secured Juniper Green Light Ten Private Limited FDRE NHPC 320 480 884 4.64 Adopted Secured Juniper Green Beta Six Private Limited FDRE NTPC 350 500 784 4.69 Adopted Secured Juniper Green Bess Zeta Private Limited FDRE SJVN 351 451 362 4.25 Adopted Secured Juniper Green Cosmic Private Limited FDRE NHPC 350 500 938 4.37 Adopted Secured Juniper Green Bess Two Private Limited Wind GUVNL 100 100 - 3.56 Adopted Secured Juniper Green Sigma Eight Private Limited FDRE TPCL 140 192 281 4.76 Adopted Secured Juniper Green Bess Delta Private Limited Wind GUVNL 50 50 - 3.65 Adopted Secured Juniper Nirjara Energy Private Limited FDRE SJVN 80 116 235 4.25 Adopted Secured Total PPA signed under construction 2,481 3,294 3,485 20
Page 21
LOA Received Projects Entity Type Off-taker AC (MW) DC (MWp) BESS (MWh) Tariff (₹/kWh) Connectivity Status Juniper Green Sigma Six Private Limited WSH SJVN 180 232 - 3.41 Secured Juniper Green Beam Six Private Limited WSH SECI 180 232 - 3.25 Secured Juniper Green Light Four Private Limited WSH SJVN 180 232 - 3.43 Secured Juniper Green Alpha Three Private Limited WSH SJVN 360 464 - 3.19 Secured Juniper Green Gem Private Limited WSH NHPC 180 239 - 3.48 Secured Juniper Green India Eight Private Limited WSH SECI 180 232 - 3.43 Secured Juniper Green Infinite Private Limited WSH NTPC 180 232 - 3.43 Secured Juniper Green India Alpha Private Limited WSH NTPC 180 232 - 3.43 Secured Juniper Green Energy Limited WSH NTPC 360 477 - 3.29 Secured Juniper Green Beam Alpha Private Limited FDRE NHPC 345 505 900 4.56 Secured Juniper Green Power Omega Private Limited FDRE NHPC 480 720 1,200 4.48 Secured Juniper Green Bess One Private Limited FDRE SJVN 250 363 600 4.25 Secured Thermal Mimic (SPV to be finalised) FDRE SECI 605 870 2,200 5.26 Secured GUVNL Wind-7 (SPV to be finalised) Wind GUVNL 50 50 - 3.51 Secured Total 3,710 5,079 4,900 21Above configuration may be revised at the time of signing of PPA or anytime beyond as per the applicable terms
Page 22
S E C T I O N 05 Annexure Image source: Juniper project asset
Page 23
Key Consolidated Financials – Snapshot TOTAL INCOME — Q2FY27 ₹372 Cr EBITDA — Q2FY27 ₹340 Cr PROFIT AFTER TAX — Q2FY27 ₹31 Cr Particulars (In INR Cr) Q2FY27 Q1FY27 Q2FY26 Revenue from operations 345 291 146 Other income 27 33 14 Total Income 372 324 160 Cost of power purchased 1 2 - Employee benefits expense 11 7 7 Other expenses 20 20 24 Total expenses 32 30 30 EBITDA 340 294 130 Finance costs 201 176 97 Depreciation and amortisation expense 99 75 58 Profit before tax 39 44 (25) Tax expense 9 11 (6) Profit after tax 31 33 (18) 23
Page 24
COMPANY: Juniper Green Energy Limited Email: investors@junipergreenenergy.com Website: www.junipergreenenergy.com Thank You Image source: Juniper project asset