FY2025 IR Presentation January 29, 2026 Code 3003
Page 2
2 Table of Contents Page 03 Executive Summary 3-5 FY2026 Forecast New Medium-and Long-term Management Plan 6 Financial Highlights (Consolidated) 7 FY2025 Income Statement (Consolidated) 8 FY2025 Segment Performance (Consolidated) 9 FY2025 Balance Sheets (Consolidated) 10 Funding 11 Financial Discipline 12 Key Metrics / Shareholder Return 13 Page 14 Portfolio Restructuring 15-16 Vacancy Rate & Rent History 17 Portfolio Distribution Pictures 18-19 Page 31 <Expanding profits on a consolidated basis> ① Raysum 32 ② Riso Kyoiku (Kodomo Depart) 33 ③ M&A 34 ④ Consolidation of “Cook Deli” 35 ⑤ Tourism-related Business 36-37 <Initiatives for “Hulic in the next 10 years”> ① Narita Logistics Development Project 38 ② Sports and Entertainment Business 39 ③ Others 40 Page 20 Ongoing Projects 21-26 Urban Data Centers 27 R&D Facilities 28 Value-added Business 29 International Business 30 Page 41 Environment 42 Social 43 Governance / External Evaluation 44 Growth Strategy (1) in Previous MT Management Plan Portfolio Restructuring Growth Strategy (2) in Previous MT Management Plan Maximizing profits from completed projects and expanding international investments Growth Strategy (3) in Previous MT Management Plan Achieving profit growth on a consolidated basis Sustainability Initiatives Consolidated Performance Summary Appendix Macro Environment 46 Progress of Leasing Portfolio Restructuring 47 FY2025 Cash Flow Statements 48 Corporate Profile 49-63
Page 3
3 FY2025 Executive Summary① ⚫ Exceeded the revised forecast. All profit items increased by over 10% • Operating profit : JPY186.8 bn, +14.3% YoY • Ordinary profit : JPY172.9 bn, +12.0% YoY • Profit attributable to owners of parent: JPY114.3 bn, +11.7% YoY ⚫ Annual dividend will be 62.0 yen, +2.0 yen from the revised forecast (Oct. 28), +8.0 yen YoY, with payout ratio of 41.1% Achieved 17th consecutive year of record-high profit and dividend per share since the listing ⚫ All financial indicators met the aiming level FY2025 Summary Real estate business: JPY198.1 bn, + JPY27.6 bn YoY / Reflected continued robust market conditions Hotels/Ryokans : JPY1.6 bn, - JPY0.0 bn YoY / Resulted flat, offsetting the rise in opening costs * 50% of hybrid finance was calculated as nominal equity FY2025 Result Aiming at around 12% or higher Dividend payout ratio Shareholder returns 41.1% Soundness D/EBITDA * Net D/E ratio * 9.2 times 1.8 times ROE around 10 times high 1x range Efficiency 13.0% 40% or higher
Page 4
4 ◼ Gross investment of JPY760.0 bn. Progress in investments in high-quality real estate drove leasing income above plan ◼ CRE acquisitions, exchange deals with our public REIT, and contributions to our private REIT and funds progressed smoothly ◼ Acquired 5 properties in Ginza, our focus area ◼ Development & reconstruction: Completed 8 projects including flagships such as Hulic Ginza Building ◼ International Business: 16 deals (over JPY70.0 bn) were confirmed/committed ◼ Raysum: Multiple joint investments executed; results outperformed the plan ◼ Hotels/Ryokans: 3 Gate Hotels and 1 FUFU opened; result outperformed the plan ◼ Child Education: The 1st Kodomo Depart opened in Nakano and Tama Plaza ◼ Executed 2 M&A deals including Cook Deli ◼ Environment: Progressed toward commercialization of the renewable electricity business ◼ New business domains: Progress in Narita Development Project (WING NRT), Makuhari Arena FY2025 Executive Summary② Initial Forecast Change Ordinary Profit Initial Forecast Change 2024 Maximizing profits from completed projects and expanding international investments 2 Portfolio Restructuring 1 +8.9bn - - 2025 Impacts of higher interest rates and debt increase Achieving profit growth on a consolidated basis Amortization of intangible assets associated with Riso Kyoiku/Raysum consolidation 154.3bn 172.9bn Result Change +6.0bn +3.0bn +0.1bn Portfolio Restructuring Maximizing profits from completed projects and expanding international investments ◼ Higher lease termination income ◼ Offset higher interest expenses from rising rates Non-operating Income /Expenses Achieving profit growth on a consolidated basis 3
Page 5
5 4Q Executive Summary ⚫ M&A: Consolidation of Cook Deli Entering the ready-to-eat meal business—an area expected to see further growth—as a solution that supports efficiency and labor shortage in the nursing care industry ⚫ Development / Reconstruction: Construction of projects in prime locations such as G8 Development Project, Aoyama Building Reconstruction Project, and the 1st R&D development, Minami-watarida North Side of the Northern District Project, has begun ⚫ Corporate Investments: Made an additional investment in satellite-related company Synspective, as an investment in start-up companies that address social issues ⚫ International Business: 7 deals (JPY35.0 bn) were confirmed/committed in 4Q ⚫ Child Education Business: Kodomo Depart Azabu began construction ⚫ Environment: 2 sites of grid scale battery storage started operation ⚫ External Evaluation: For 2 consecutive years, rated 4.5 stars in Nikkei SDGs Management Survey and selected for the 2025 Climate Change “A” List by the CDP Development and M&A both progressed in 4Q
Page 6
6 Have been working on the formulation of a new Medium-and Long-term Management Plan (LTP) in light of drastic changes in the business environment and uncertainties, in addition to making progress toward achieving the target of JPY180.0 bn in consolidated ordinary profit set in the previous LTP. Scheduled to be announced on February 3, 2026. ⚫ Plan to achieve 18th consecutive year of record-high profit and dividend per share since the listing, sustaining high growth in all profit items ⚫ Increase annual dividend by 5.0 yen, payout ratio 42.0% (plans to enhance shareholder returns) FY2026 Forecast New Medium-and Long-term Management Plan New Medium-and Long-term Management Plan (2026-2036) FY2025 Result FY2026 Forecast Change Operating Revenue 727.4 - - (bn yen) Operating Profit 186.8 210.0 +23.1 (bn yen) Ordinary Profit 172.9 185.0 +12.0 (bn yen) Profit attributable to Owners of Parent 114.3 121.0 +6.6 (bn yen) Annual Dividend 62.0 67.0 +5.0 (yen) FY2026 Forecast
Page 7
7 63.6 69.5 79.1 94.6 102.3 114.3 (121.0) 0.0 20.0 40.0 60.0 80.0 100.0 120.0 20/12 21/12 22/12 23/12 24/12 25/12 26/12 (Billion yen) 17 consecutive years of record profits; on track in achieving the previous mid-term plan target of over JPY180.0 bn in consolidated ordinary profit Financial Highlights (Consolidated) 339.6 447.0 523.4 446.3 727.4 0.0 200.0 400.0 600.0 20/12 21/12 22/12 23/12 24/12 25/12 26/12 (Billion yen) 100.5 114.5 126.1 146.1 163.3 186.8 (210.0) 0.0 50.0 100.0 150.0 200.0 20/12 21/12 22/12 23/12 24/12 25/12 26/12 (Billion yen) (Billion yen) 95.6 109.5 123.2 137.4 154.3 172.9 (185.0) 0.0 50.0 100.0 150.0 200.0 20/12 21/12 22/12 23/12 24/12 25/12 26/12 (N/A) Operating Profit Ordinary Profit (Recurring Profit) Profit attributable to Owners of Parent Operating Revenue (forecast) (forecast) (forecast) 591.6
Page 8
8 Offsetting the increase in interest expenses due to rising interest rates, ordinary profit, net income increased by about 12% FY2025 Income Statement (Consolidated) (Million yen) FY24/12 FY25/12 Change (%) Operating Revenue 591,615 727,447 135,831 (+22.9%) Operating Gross Profit 230,934 276,802 45,868 SGA Expenses 67,573 89,976 22,403 Operating Profit 163,360 186,826 23,465 (+14.3%) Non-operating Income 6,791 13,639 6,847 Non-operating Expenses 15,822 27,538 11,715 Ordinary Profit (Recurring Profit) 154,329 172,927 18,597 (+12.0%) Extraordinary Income 6,333 4,467 -1,866 Extraordinary Losses 9,527 6,052 -3,474 Total Income Taxes 47,845 56,081 8,236 Profit attributable to Owners of Parent 102,341 114,334 11,993 (+11.7%) Major factors for changes Gain on sale of investment securities -2.1 bn Real Estate Business +10.0 bn Hotels / Ryokans +4.9 bn Loss on step acquisitions incurred in FY2024 -2.7 bn Real Estate Business +110.2 bn Hotels / Ryokans +5.1 bn Interest expenses +8.5 bn Raysum M&A fees +1.4 bn
Page 9
9 (Million yen) FY24/12 FY25/12 Change Operating Revenue 591,615 727,447 135,831 Real Estate 527,204 637,458 110,253 Raysum - 136,838 136,838 Insurance Agency (subsidiary) 3,699 3,929 230 Hotels / Ryokans (subsidiaries) 49,092 54,256 5,163 Others 25,814 45,643 19,829 Riso Kyoiku 17,828 33,931 16,102 Elimination / Corporate -14,195 -13,840 355 Operating Profit 163,360 186,826 23,465 Real Estate 170,428 198,111 27,683 Raysum *Pre-goodwill amortization - 25,549 25,549 Insurance Agency (subsidiary) 997 1,090 93 Hotels / Ryokans (subsidiaries) 1,675 1,670 -5 Others 2,233 2,137 -95 Riso Kyoiku *Pre-goodwill amortization 2,147 2,459 312 Elimination / Corporate -11,974 -16,184 -4,209 % Stable Core Profits*1 36.6% 36.5% Real Estate OP rose JPY27.6 bn (16%), with Raysum outperforming plan by JPY2.0 bn Hotels/Ryokans remained roughly flat due to higher opening costs but well above plan FY2025 Segment Performance (Consolidated) Leasing revenue, etc. +20.6 bn Acquired / completed / existing properties +16.0 bn Transfer to real estate for sale -8.3 bn Others +12.9 bn Sales revenue +89.6 bn Increase in opening costs-0.3 bn Increase in Rev/Par +0.3 bn Major factors for changes *1: Deducting real estate sales profit from consolidated operating profit. Elimination and corporate were allocated to reportable segments and Others. *2: Before allocating elimination and corporate *Change in accounting treatment for development land rents Stable core profits +8.4 bn Real estate sales profit +14.9 bn Raysum: Actual vs. Plan +2.0 bn Leasing profit, etc.*2 +10.0 bn Existing / acquired / completed properties +10.8 bn Transfer to real estate for sale -5.3 bn Others +4.6 bn Sales profit*2 +17.6 bn
Page 10
10 Non-current Assets and Investment Securities increased reflecting steady investments Net Assets also increased up to JPY940.0 bn FY2025 Balance Sheets (Consolidated) 24/12 25/12 Change Current Assets 583,864 686,528 102,664 Cash and deposits 134,462 131,083 -3,378 Inventories 405,111 425,953 20,841 Operational investment securities 9,740 78,280 68,539 Non-current Assets 2,463,680 2,817,797 354,117 Property, Plant and Equipment 1,723,825 1,927,374 203,549 Intangible Assets 216,886 258,822 41,936 Investment Securities 420,487 499,499 79,012 Marketable Securities 174,593 227,638 53,045 Shareholdings/Investments of Affiliated Companies, etc. 245,894 271,861 25,967 Total 3,048,935 3,506,068 457,132 Liabilities 2,192,591 2,566,887 374,296 Borrowings 1,397,089 1,607,396 210,307 Corporate Bonds 473,909 603,856 129,946 Deferred Tax Liabilities 89,978 107,248 17,269 Net Assets 856,344 939,180 82,835 Shareholders’ Equity 769,176 829,364 60,187 Valuation Difference on Available-for-sale Securities 65,506 85,176 19,670 Total 3,048,935 3,506,068 457,132 Major factors for changes (Million yen) Net income +114.3 bn Cash dividends paid -43.3 bn Elimination upon full consolidation of Raysum -7.5 bn Purchase of treasury shares (BBT) -3.1 bn AssetsLiabilities & Net Assets Real estate investment through SPC, etc. +52.7 bn MTM valuation +30.0 bn CP issuance based on mid-term CF +90.0 bn Annual plan-based procurement +210.3bn Land・Buildings +173.7 bn Acquisitions, completions +355.2 bn Transfer -177.8 bn Others (Depreciation, etc.) -3.7 bn
Page 11
11 Utilizing short-term borrowing amid the current market environment, while proactively securing long-term funding when rates ease Funding JCR rating AA- / Stable External Rating Corporate Bonds Short-term Borrowing Capacity Average Funding Cost & Long-term Borrowing Ratio 2020/12 2021/12 2022/12 2023/12 2024/12 2025/12 0.72% 0.71% 0.77% 0.80% 0.84% 1.15% (As of the end of 2025) (Billion yen) OD limit (unused balance) 154.0 (154.0) CP issue limit (〃) 200.0 (80.0) Added SB limit (〃) 300.0 (140.0) (*) Average interest rate including hybrid finance: Date Coupon rate (%) JPY (bn) Tenor (year) Oct. 22, 2018 6th Straight 0.494 20.0 10 Jun. 25, 2019 8th Straight 0.30 20.0 7 〃 9th Straight 0.40 15.0 10 Jul. 2, 2020 3rd Hybrid 1.40 40.0 37 (NC7) 〃 4th Hybrid 1.56 40.0 40 (NC10) Oct. 15, 2020 10th Straight (*) 0.44 10.0 10 Oct. 19, 2022 5th Hybrid 1.435 46.0 35 (NC5) 〃 6th Hybrid 1.849 30.0 40 (NC10) Apr. 13, 2023 11th Straight 0.320 40.0 3 Feb. 29, 2024 12th Straight 0.610 13.0 5 Apr. 18, 2024 13th Straight 0.569 30.0 3 〃 14th Straight 0.806 20.0 5 Mar. 6, 2025 7th Hybrid 2.102 60.0 35 (NC5) Jul.10, 2025 15th Straight 1.529 100.0 5 Total (bn) 484.0 (*) Sustainability Linked Bonds 99.9 99.9 99.9 99.8 89.4 94.1 97.9 0.56 0.56 0.57 0.60 0.67 1.00 0.50 1.00 1.50 2.00 2.50 3.00 0 20 40 60 80 100 20/12 21/12 22/12 23/12 24/12 25/12 Long-term borrowing ratio Average interest rate (*) (%) (%) Due to bridge loans related to the tender offer for Raysum (Raysum adjusted) considering interest rate environment
Page 12
12 With thorough B/S control, Net D/E ratio and D/EBITDA ended within our target range ROE also remained high at 13% Financial Discipline Safety and Efficiency Financial Discipline 486.4 637.7 686.7 765.6 832.9 913.2 32.7 36.8 37.1 37.9 33.0 31.0 13.4 12.3 11.9 13.0 12.8 13.0 0.0 20.0 40.0 60.0 0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0 800.0 900.0 20/12 21/12 22/12 23/12 24/12 25/12 Equity Equity ratio* ROE (Billion yen) (%) 1,360.1 1,394.4 1,440.9 1,445.0 1,870.9 2,211.2 1.7 1.3 1.3 1.3 1.6 1.8 9.9 9.0 8.5 7.6 9.1 9.2 0.0 2.5 5.0 7.5 10.0 0.0 500.0 1,000.0 1,500.0 2,000.0 20/12 21/12 22/12 23/12 24/12 25/12 Total interest-bearing debt Net debt to equity ratio* Net debt to EBITDA ratio*(Billion yen) (times) *50% of hybrid finance (175.0 bn=JPY350.0 bn x 50%) was calculated as nominal equity
Page 13
13 Steady EPS growth and 17 consecutive years of dividend increase. Payout ratio at a record-high 41.1%. 2026 annual dividend plan is 67.0 yen (+5.0 yen YoY) Key Metrics / Shareholder Return 95.23 101.09 104.00 124.36 134.42 150.50 159.35 20/12 21/12 22/12 23/12 24/12 25/12 26/12 0.00 50.00 100.00 150.00 (Yen) 728.31 836.89 902.70 1,006.19 1,093.78 1,202.76 20/12 21/12 22/12 23/12 24/12 25/12 0.00 500.00 1,000.00 (Yen) (Yen per Share) 25.50 31.50 36.00 39.00 42.00 50.00 54.00 62.00 67.00 33.9% 35.4% 37.8% 38.5% 40.3% 40.2% 40.1% 41.1% 42.0% 15.0% 20.0% 25.0% 30.0% 35.0% 40.0% 45.0% 0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 18/12 19/12 20/12 21/12 22/12 23/12 24/12 25/12 26/12 Annual Dividend (Left axis) Payout ratio (Right axis) (forecast) (forecast) EPS (Net income per share) BPS (Book value per share) Dividend History
Page 14
14 Portfolio Restructuring Restructure the portfolio to achieve “high profit growth” and “stable core profit increase” Previous Medium-Term Management Plan Growth Strategy (1)
Page 15
15 FY2025 cumulative investment stood over JPY760.0 bn (gross amount). Investment progressed in focus areas (Ginza 5, Shibuya 2, Shinjuku 1) and in data centers Portfolio Restructuring Major Investment in 2025 (■Assets in focus areas) Settlement Asset type Property summary 1Q Office ■FORECAST Shinjuku SOUTH [1st settlement of two installments] Retail ■PUZZLE GINZA Retail ■2 retail facilities in Ginza area *Mezzanine investment Shopping mall Ario Nishiarai [2nd settlement of two installments] R&D facilities/CRE JFE Minami-watarida North Side of the Northern District Development land CRE Land of 2 properties owned by an educational institution in Tokyo CRE 2 YAMATO TRANSPORT warehouse 2Q Office Hulic Kamiyacho Building (35%) Office JTB Osaka Building (land) Hotel Bulk acquisition (4 hotels) Data center Data center in Greater Tokyo *Equity investment R&D facilities/CRE Nipro Tokyo CPF (land) Settlement Asset type Property summary 3Q Office ■FORECAST Shinjuku SOUTH [2nd settlement of two installments] Office FUJI SOFT Akihabara Building Office Hulic Kamiyacho Building (56%) Retail ■Ginza 5-chome 3-9 Development Project Hotel Hotel in Roppongi (land) Senior living Plaisant Grand Senzoku Network Center Ikebukuro / Nagano Network Center 4Q Office ■NREG Ginza Building Office ■Office in Shibuya Development land Office development land in Tokyo 5 wards Retail ■Hulic Shibuya Miyamasuzaka Building Shopping mall Luz Musashi-kosugi Shopping mall mioka *equity investment Data center Nisshincho Data Center (land) Others
Page 16
16 Group REITs & fund AUM expanded up to JPY870.0 bn. Exchange transactions with our public REIT and sales to our private REITs/funds progressed Portfolio Restructuring Major properties sold Reasons to sell Property name Asset type Sold date Transfer within the Hulic Group Exchange transactions with Hulic Public REIT Hulic Shinjuku Building (41%) Office Jun. 2025 Asakusa View Hotel Hotel Sep. 2025 Transfer to Hulic private REIT/funds 4 office buildings, Property A, Property B(49%) Office, etc. Mar. 2025 Property C(49%) Retail Sep. 2025 2 logistics centers, Property D(49%) Logistics centers, etc. Dec. 2025 Portfolio restructuring (e.g., seismic reinforcement, value-add initiatives) 4 office buildings Office Mar.-May 2025 Tsukiji Yasuda No.2 Building Office Sep. 2025 Hotel Resol Yokohama Sakuragicho Hotel Sep. 2025 Review of development plans 2 development land Development land Mar. 2025 Hulic Osaka Building Office Dec. 2025 Review of S-class office assets Yaesu 1-Chome East Area Category-I Urban Redevelopment Project (District B) *Our equity interest only Office Nov. 2025 Yaesu 2-Chome Central District Category-I Urban Redevelopment Project *Our equity interest only Office Dec. 2025 Acquired Hulic Kamiyacho Building (91%) Exchange
Page 17
17 Average rents remained high, with YoY decline due to reconstruction progress, etc. Vacancy Rate & Rent History 5.4 4.0 3.6 3.1 1.8 1.5 4.4 6.3 6.4 6.0 4.0 2.2 0.7 0.9 0.3 0.4 0.4 0.2 0.6 0.5 0.6 0.4 0.2 0.4 0.6 1.3 0.4 0.6 0.4 0.1 0.8 0.7 0.9 0.7 0.3 0.7 0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 0 5,000 10,000 15,000 20,000 25,000 30,000 2014/12 2015/12 2016/12 2017/12 2018/12 2019/12 2020/12 2021/12 2022/12 2023/12 2024/12 2025/12 Hulic Office in Tokyo 5 wards Market average in Tokyo 5 wards Market average in Tokyo 5 wards All Hulic Hulic in Tokyo 23 wards Hulic 5 wards 25,147 24,510 24,970 25,242 25,628 27,858 28,393 28,119 28,478 27,334 28,415 26,111 Tokyo 5 wards 16,953 17,692 18,540 19,173 20,887 22,206 21,999 20,596 20,059 19,748 20,296 21,409 Osaka 6 wards 11,123 11,114 11,051 11,267 11,423 11,794 11,925 11,796 11,872 11,976 12,170 12,750 23,207 23,691 22,549(The average of all Hulic buildings) Average office rent (yen/tsubo) (Average rent: yen per tsubo=3.3㎡) (Vacancy rate:%) ・Market average data: MIKI SHOJI “Office Data by regions” (Tokyo Business District building with more than 100 tsubo as a base f loor space) ・Hulic vacancy data excluded refurbishing spaces, leasing floor space within 1 year from completion and real estate for sale ・Hulic’s rent data: period-end monthly rent income ÷ period-end contracted floor, excluded hotel / ryokan, single -tenant lease and real estate for sale
Page 18
18 Holding a well-balanced portfolio with a focus on centrally located and near-station properties. Marginal growth on unrealized gains on leasing properties and investment Portfolio Distribution Pictures 5 min or less 72% Property Age (for all assets)Walking Distance from Train Stations (for office building, etc.) Distribution of Portfolio (for office building, etc.) ※ As of Dec. 31, 2025 Less than 10 years 49% Over 40 years 12%30-40 years 12% 20-30 years 10% 10-20 years 17% To be reconstructed in near future 250 properties Number of Properties Net Leasable Area Greater Osaka 4% 1,200 K㎡ Tokyo 5 wards 46% Other Tokyo 23 wards 21% Tokyo 5 wards 30% Other 6% Other 9% Other Tokyo 23 wards 23% Tokyo suburbs 37% Tokyo suburbs 20% 206 properties Greater Osaka 4% 1min or less 32% 2-3 minutes 27% 4-5minutes 13% 5 minutes or more 28% 206 properties 293.3 323.2 370.0 353.0 364.6 375.8 384.9 402.9 409.9 0.0 100.0 200.0 300.0 400.0 17/12 18/12 19/12 20/12 21/12 22/12 23/12 24/12 25/12 Unrealized gains (= NAV - book value) (Billion yen) 1,075 1,198 1,382 1,351 1,323 1,362 1,387 1,279 1,316 12 21 21 159 180 180 197 858 787 0 500 1,000 1,500 2,000 2,500 17/12 18/12 19/12 20/12 21/12 22/12 23/12 24/12 25/12 Leased land area Net leasable area Net leasable area (Including leased land area) (1,000㎡ ) Note: Non-consolidated SPCs are excluded in the calculations. Rent revenue calculations include both Otemachi Place and Dentsu H eadquarters Building Unrealized gains ・Properties under development that the Company and its subsidiaries are leasing or plan to lease after completion (excluding real estate for sale) ・Including the Company and its subsidiaries are using (excluding “Hulic Head Office Building” and its subsidiaries are using a s hotels / ryokans ) ・Major properties are appraised by appraisers. Other properties are calculated by the company using indicators believed to app ropriately reflect market prices ・The book value of properties newly acquired during the fiscal year is considered to be the fair value at the end of the period
Page 19
19 Portfolio Distribution Pictures (Sources of Rent Revenue) Office 46% ※excluding real estate for sale, including Otemachi Place and Dentsu Headquarters Building ※ Dec. 2025 (Monthly breakdown) Office 44% ◼ In response to decrease in office demand due to population decline, keeping office ratio at 50% or less. Although, focusing on offices with features suited to their location ◼ Securing competitive advantages by focusing on central Tokyo, close to stations, highly earthquake resistant, and renewable energized buildings Office (Mizuho) 2% Rental apartments 1% Senior living 5% ◼ Owning over 4,900 rooms, contributing to stable earnings ◼ Halted new development Hotel, Ryokans 13% ◼ Expanding directly operated facilities ◼ Targeting the upper middle to the high-net-worth ◼ Expanding in carefully selected areas, achieving high occupancy rates and high ADRs Retail Commercial 24% ◼ Expanding in prime areas such as Ginza where high demand from luxury brands continues ◼ Achieving high rent mainly in street-level shops Data Center 6% ◼ Actively investing as an asset resilient to inflation ◼ Opting for urban data center developments Others 5% R&D facilities、logistics、Kodomo Depart, etc.
Page 20
20 Maximizing profits from completed projects and expanding international investments Maximize profits from completed projects and promote carefully selected development projects in response to the changing external environment Previous Medium-Term Management Plan Growth Strategy (2)
Page 21
21 Completed bank reconstructions in Ginza & Sapporo and the first urban data center Projects Completed in 2025 Property Name Area Asset type Total Floor Space (Approx.) Completion 1 Kodomo Depart Nakano Tokyo 23 wards Kodomo Depart 2,100㎡ 1Q 2 Hulic Logistics Noda II Greater Tokyo Logistics 16,700㎡ 1Q 3 Hulic Logistics Misato Greater Tokyo Logistics 56,900㎡ 3Q 4 Hulic Nihonbashi Center Tokyo 5 wards Data center 6,300㎡ 3Q 5 LICOPA Higashi Yamato Greater Tokyo Shopping mall 49,900㎡ 3Q 6 ■●Hulic Ginza Building Focus area / Ginza Ryokan, office, retail 12,800㎡ 3Q 7 ●HULIC SQUARE SAPPORO II Sapporo Hotel, office, retail 22,400㎡ 3Q 8 FUFU Jogashima Greater Tokyo Ryokan 4,800㎡ 4Q ■ Assets in focus areas ●Reconstruction of bank branch building 1 4 2 3 6 7 8 5
Page 22
22 Large projects, Quartz Shinsaibashi and Jiyugaoka, along with three Ginza properties are set for completion Projects to be Completed in 2026 ■ Assets in focus areas Property Name Area Asset type Total Floor Space (Approx.) Completion 1 Quartz Shinsaibashi Osaka Retail, office, hotel 46,200㎡ 2026 1Q 2 ■World Town Building Renovation Project Focus area / Ginza Retail 4,100㎡ 2026 2Q 3 One’s Mall Renovation Project Greater Tokyo Retail 83,800㎡ 2026 2Q 4 Jiyugaoka 1-29 Redevelopment Project Tokyo 23 wards Retail, Kodomo Depart, office, etc. 46,000㎡ 2026 3Q 5 ■Nishi Ginza Development Project Focus area / Ginza Retail, office 7,300㎡ 2026 3Q 6 Property in Kichijoji Greater Tokyo Retail 1,000㎡ 2026 3Q 7 Miyazaki Prefecture Tokyo Building Redevelopment Project (PPP) Tokyo 5 wards Office 5,100㎡ 2026 3Q 8 ■Ginza 8-chome 9-11, 12 Development Project Focus area / Ginza Retail 5,500㎡ 2026 4Q 1 2 3 4 5 7 8
Page 23
23 In Shinsaibashi, street-front luxury brands and THE GATE HOTEL are set to open, while Jiyugaoka will feature a full-floor “Kodomo Depart” Projects to be Completed in 2026 —Quartz Shinsaibashi and Jiyugaoka— Jiyugaoka 1-29 Redevelopment ProjectQuartz Shinsaibashi Address 3-12-14 Minamisemba, Chuo-ku, Osaka-shi, Osaka Access Direct to Shinsaibashi station, Osaka Metro Floor area 46,241㎡ Completion Mar. 2026 Address In the 1-29 Jiyugaoka area, Meguro-ku, Tokyo Access 1 min walk from Jiyugaoka station, Tokyu Lines Floor area Approx. 46,000㎡ Completion 3Q 2026 6F Office • Approx. 132m tall, serving as a new Shinsaibashi landmark that enhances the area’s vibrancy • Tenants to open sequentially after the Apr. 25 grand opening B1-4F Retail 16-28F Hotel 8-14F Office THE GATE HOTEL Osaka by HULIC (Open in Jun. 2026) Details: page 37 B2-6F Retail, clinics 7-14F Rental housing (Approx. 170 units) 5F Kodomo Depart (Child education facility) 1-3F Street level stores Luxury brands (Bulgari, Cartier, Fendi, Chaumet, etc.) Anchor tenants MEIDI-YA (Supermarket) SHARE LOUNGE Diverse food, trend, fashion, and lifestyle stores to open under the ‘FINE QUALITY LIFE’ concept • Commercial areas to open in fall 2026 • North-south shopping passage and pedestrian paths around the building on the first floor to improve convenience Leasing completed with diverse tenants Childcare, early learning classes, pediatric clinics, cooking schools, Kodomo Depart Studio, etc.
Page 24
24 Construction will begin at 3 Ginza projects including Ginza Core (Ginza 5-chome Development Project) and projects in Omotesando Projects Starting Construction in 2026 Property Name Area Asset type Total Floor Space (Approx.) Start of Construction Completion 1 FUFU Kyu-Karuizawa Annex Development Project Nagano Ryokan 2,800㎡ 1Q 2027 2 Minami-watarida North Side of the Northern District Project / R&D center A Greater Tokyo R&D facility 13,300㎡ 1Q 2028 3 ■Ginza 5-chome Development Project (Ginza Core) Focus area / Ginza Retail 20,900㎡ 1Q 2028 4 Property in Nishi-Nippori Tokyo 23 wards Child education 3,500㎡ 2Q 2028 5 ■Ginza 6-chome Miyuki St. Development Project Focus area / Ginza Retail 5,900㎡ 3Q 2028 6 Senior living in Sendagaya Tokyo 5 wards Senior living 2,400㎡ 3Q 2027 7 ■Omotesando Development Project I Focus area / Shibuya & Aoyama Retail 1,500㎡ 3Q 2028 8 Akihabara Chuo St. Development Project Tokyo 5 wards Retail 1,500㎡ 3Q 2027 9 ■Ginza 5-chome 3-9 Development Project Focus area / Ginza Retail 350㎡ 4Q 2027 5 R&D Center A 3 2 Under demolition ■ Assets in focus areas Architectural Design visualizing : ©️TAISEI CORPORATION City visualizing: Vexcel Imaging US inc.©️2021-2025
Page 25
25 No Image 1 1 2 3 5 6 7 8 Strategically important area for stable leasing income and unrealized gains, with 39 properties held and two more secured. 8 projects underway following the 2025 completion of HulicGinza Building Projects in Ginza Area Acquired through external sources Development projects (completed) Development projects (progressing) Note: Information on this page is based on current plans and is subject to change due to changes in design, discussions with related government ministries and agencies, etc. New Ginza 5-chome 3-9 Development Project Complete in 2027 (plan) 4 G8 Development Project Complete in 2028 (plan) 5 Ginza 6-chome Miyuki St. Development Project Complete in 2028 (plan) 6 Ginza 7-chome Showa St. Development Project Complete in 2029 (plan) 7 Under demolition Ginza 5-chome Development Project Complete in 2028 (plan) ◼ We seek to maximize earnings through increasing floor-area ratio by taking advantage of Ginza district plans upon reconstruction 8 Ginza 8-chome 9-11, 12 Development Project Complete in 2026 4Q (plan) 3 4 Complete in 2026 3Q (plan) Nishi Ginza Development Project Complete in 2026 2Q (plan) World Town Building Renovation Project 2 1 After the renovation, NOI (forecast): ×1.4times Under demolition
Page 26
26 Development is also progressing in Shibuya / Aoyama, and Shinjuku east-exit area A new THE GATE HOTEL is planned to open at Shinjuku east-exit area Projects in Other Focus Areas Shibuya / Aoyama area Shinjuku east-exit area No Image Shinjuku 318 Development Project ◼ 1 min walk from Shinjuku station, Tokyo Metro Line ◼ Underground demolition began in Dec. 2025 1 min walk from station ◼ Complete in 2028 ◼ Asset type: retail, office ◼ 1 min walk from Omotesando station ◼ Construction work began in Nov. 2025 Aoyama Building Reconstruction Project1 min walk from station By increasing rent revenue, NOI:×4.0times (forecast) ◼ Complete in 2027 ◼ Asset type: office, rental housing, Kodomo Depart, retail, multi- purpose hall, etc. ◼ 1 min walk from Shibuya station ◼ Construction began in Jul. 2024 Shibuya 1-chome Area Joint Development Project 1 min walk from station ◼ Complete in 2028 ◼ Asset type: retail ◼ 2 min walk from Omotesando station, Tokyo Metro Lines ◼ Demolition began in Jan. 2025 Omotesando Development Project I Under demolition 2 min walk from station Note: Information on this page is based on current plans and is subject to change due to changes in design, discussions with related government ministries and agencies, etc.
Page 27
27 Focused Asset Class: Urban Data Centers Hulic Nihonbashi Center began operations in Oct. 2025 Actively pursuing further expansion opportunities Shiohama 2-chome Development Project Initiatives for Urban Data Centers Hulic Nihonbashi Center ◼ With the rapid growth in domestic data traffic, urban data centers are emerging as a high-growth market. They provide high- speed, high-capacity, and low-latency connectivity, particularly in densely networked Tokyo central areas ◼ While many competitors are focusing on suburban sites, we have taken an early lead in developing urban data centers and are currently advancing five projects ◼ Recognizing their resilience to inflation, we intend to actively pursue further development of urban data centers Project Pipeline Location Completion (plan) IT load capacity 1 Hulic Nihonbashi Center Chuo-ku, Tokyo 2025 5MW 2 Shiohama 2-chome Development Project Koto-ku, Tokyo I : 2027 6MW 3 II : 2029 24MW 4 Project C Koto-ku, Tokyo 2031 33MW (Plan) 5 Project D Chiyoda-ku, Tokyo 2031 16MW (Plan) • Effective land utilization project of Tokyo Metro (Tokyo-central subway company) (CRE; Corporate Real Estate) garage. Construction started for Phase I • Geographical superiority: Close to major interconnection points for data transmission; Otemachi & Toyosu & little risk of flooding Otemachi Shiohama 2-chome Toyosu Minato Chuo Chiyoda Koto Project Plan Address Shiohama 2-chome, Koto- ku, Tokyo Access 10 min walk from Toyo-cho Station (Tokyo Metro) Completion I : 2027, II : 2029 (Plan) 2 Note: Information on this page is based on current plans and is subject to change due to changes in design, discussions with related government ministries and agencies, etc. Inland location close to major interconnection points • Our first data center project: close to Otemachi's interconnection hubs, ensuring high connectivity. Strong demand confirmed in leasing Project Plan Address Nihonbashi, Chuo-ku, Tokyo Land Approx. 967㎡ # of floors 8F - B1 Completion Sep. 2025 1 • Co-established an operating company for the Kobuna-cho data center with an experienced data center operator “Digital Edge DC”
Page 28
28 Focused Asset Class: R&D Facilities New construction began at the end of 2025, city opening planned for Spring 2028 Confirmed strong demand for multi-tenant lease labs during pre-leasing Project Plan Address 13-1 etc. Minami-watarida-cho, Kawasaki-ku, Kawasaki-shi, Kanagawa Land 5.7ha(57,000㎡) *Hulic will develop 4ha(40,000㎡) Asset type R&D and related facilities Opening date Spring 2028 (Plan) ◼ CRE (corporate real estate) initiative where Hulic was selected as the business partner in JFE Holdings’ call for proposals ◼ R&D center A will be solely tenanted by JFE, while Center B is developed as multi-tenant rental labs with excellent accessibility, enabling experiments including handling hazardous materials and high-pressure gas that are difficult in central Tokyo ◼ In Mar. 2025, acquired 4ha land for our development project R&D Facilities:Minami-watarida North Side of the Northern District Project An approx. 5.7ha of rare development site with high transportation convenience ✓ 3 min walk from the nearest station ✓ 3km from JR/Keikyu Kawasaki Station ✓ 5km from Haneda Airport Note: Information on this page is based on current plans and is subject to change due to changes in design, discussions with related government ministries and agencies, etc. To Hama-Kawasaki Station Layout plan R&D zone Supportive zone R&D center (image) Community center (image)
Page 29
29 World Town Building renovation to be completed in June LICOPA Higashi Yamato Terrace fully leased (11 units) with all stores opening by Apr. Value-added Business World Town Building Renovation Project LICOPA series (renovation of GMS) ◼ As a general merchandise store (GMS) total renovation project, we are developing “LICOPA”, a community-focused retail facility ◼ Three Ito-Yokado stores have been converted to LICOPA, through renovations, expansions, and tenant reshuffling, leading to higher NOI Name Location Total floor (approx.) Open VA scheme 1 LICOPA Tsurumi Yokohama-shi, Kanagawa 31,935㎡ Sep. 2021 Renewal 2 LICOPA Kawasaki Kawasaki-shi, Kanagawa 5,660㎡ Mar. 2024 Building extension 3 LICOPA Higashi Yamato Higashiyamato -shi, Tokyo Maison building 46,800㎡ Nov. 2024 Renewal Terrace building 3,100㎡ Sep. 2025 Building extension ◼ Seismic reinforcement and full façade renovation are planned ◼ Profitability greatly enhanced by expanding street-level retail space and increasing rent ◼ Construction carried out while tenants remain in operation 1 2 3 Maison building (Opened in Nov. 2024) Address 5-8-17 Ginza, Chuo-ku, Tokyo Total floor Approx. 4,120㎡ # of floors 8F / B2 Access 1 min walk from Ginza Station, Tokyo Metro Lines Completion Jun. 2026 3 Terrace building (Opened in Sep. 2025) After the renovation, NOI:×1.4times (forecast) One’s Mall Renovation Project Renovation underway in two phases; Phase 2 to open in Spring 2026 Address 330-50 Naganumacho, Inage-ku, Chiba-shi, Chiba Total floor Approx. 83,700㎡ # of floors 6F Access Approx. 1.8 km from Anagawa IC, Keiyo Road Completion May 2026
Page 30
30 International Business 7 deals (JPY35.0 bn) were confirmed/committed under risk-controlled schemes in 4Q Cumulative investment reached approx. JPY100.0 bn Basic Strategy and Progress • Risk-mitigating strategy: allocating JPY1.0-7.0 bn per case, partnering with Japanese companies with rich track records in international investments, etc. • The newly established Global Investment Department enhances deal sourcing and ongoing project management Investment Strategies Areas Population / Economic growing countries Asset Class Asset class with solid demand Balanced investments with a focus on operational properties Scheme Small- to medium-lot investments, Diverse investment scheme, Partnership with Japanese companies U.S. Singapore Vietnam India Senior living Houses built for sale Rental housing Industrial assets (Logistics, plants) Equity investment Mezzanine investment Fund investment Joint investment Example Rental factories and logistics warehouses in India Major investments in 2025 U.S. Senior living Savanna House / Arizona McDowell Village / Arizona Overture Hamlin / Florida The Bellettini / Washington Rental housing Turing / California The Danforth / Washington Project A / Texas Student housing Kinetic / Georgia Singapore Logistics center Sunview Logistics (BTS development project) 20TSA Vietnam Rental factory Core5 / near Hanoi and Hai Phong India Houses built for sale Debt fund for development projects Rental factories /logistics warehouses Ranjangaon PJ and Sri City PJ • Invested in two high-occupancy industrial properties (rental factories and logistics warehouses) in Pune and Chennai in 4Q • A co-investment with Logicap Management (Hillhouse Group), which has extensive investment track record in India Ranjangaon PJ (Pune) Sri City PJ (Chennai) • Leased to global tenants targeting India’s large population and strong domestic consumption
Page 31
31 Achieving profit growth on a consolidated basis Build a foundation for new profit pillars by looking ahead to the next 10 years ~ expand profits on a consolidated basis ~ Previous Medium-Term Management Plan Growth Strategy (3)
Page 32
32 FY2025 results exceeded our initial plan Multiple joint investments materialized. Shift to parent-subsidy loans also progressed Expanding profits on a consolidated basis① Raysum Aiming at reinforcing value-add operations and growing the pipeline, we made Raysum our wholly-owned subsidiary in Mar. 2025 Examples of Synergy-Generating InitiativesExpected synergies Procurement and due diligence capabilities to identify further potential value Experience in handling various assets / Expertise in value-added initiatives Ability to make proposals to accurately address customer needs; a wide-ranging customer base Sector-leading capability in collection of information for real estate sourcing Diverse exits including Hulic Group REITs Ability to stably raise funds at low cost Realize further growth and sustainable enhancement of corporate value on a consolidated basis by incorporating a new real estate business model • Jointly invested in a bulk deal: a scheme in which Raysum acquired properties outside our investment criteria • Sharing information on transaction opportunities sourced through our channels FY2025 results Procure- ments • Diversifying exit strategies using each other’s customer base Exits • Sequentially shifting to parent-subsidiary loans (financing from Hulic to Raysum) Approx. 60% has been switched as of the end of 2025 Funding • FY2025 operating profit was JPY25.5 bn (before goodwill amortization), exceeding our initial plan • The pipeline of properties held for sale stood at approx. JPY120.0 bn
Page 33
33 Received Kids Design Award. New openings in Jiyugaoka, Shibuya, Motoyawata, and Azabu. Attracting many inquiries Expanding profits on a consolidated basis② Riso Kyoiku (Kodomo Department) Kodomo Depart Nakano Kodomo Depart Tama Plaza 1F Cafe 2F 5-6F 3F 4F 9F 7-8F ◼ 2 min walk from JR Nakano station ◼ 9-story building Future pipeline Coming soon 6 min walk from Shirokane takanawa Sta. 1 min walk from Jiyugaoka Sta. 2 min walk from Shibuya Sta. Aim developing approx. 20 facilities mainly in Greater Tokyo area by 2029 Sep. 2026 2027 2028 etc. Operated by Riso Kyoiku Group (Consolidated subsidiary) Operated by KONAMI Sports (Business alliance partner) Kodomo Depart Jiyugaoka (Opening in limited floors) Kodomo Depart Shibuya (Opening in limited floors) 1F 2F 3F ◼ 2 min walk from Tama Plaza station, Tokyu Den-en-toshi Line ◼ 3-story building Kodomo Depart Azabu (Opening in limited floors) Women-only Pilates Sports classes Exam prep tutoring Tutoring, English classes, Preschool for infants Offering a wide-range of extra- curricular & family programs Pediatrics & sick-child care After-school care with tutoring Preschool classes Childcare & educational play After-school care with tutoring Offering a wide-range of extra- curricular & family programs Received Kids Design Award Chairman's Award for its novelty, support for dual-income families, and contribution to enhancing the appeal of the area Kodomo Depart Won the 19th Kids Design Award 2 min walk from MotoyawataSta. Kodomo Depart Motoyawata (Opening in limited floors) Construction began in Nov, 2025
Page 34
34 Aiming to strengthen our consolidated earnings through M&As Expanding profits on a consolidated basis③ M&A Achievements in FY2025 ◼ Expansion into the child education business due to increasing dual-income households and government childcare support, etc. ◼ Made the company a consolidated subsidiary on May 28, 2024, to strengthen our child education business Consolidation of Riso Kyoiku Group (Announced in Apr. 2024) ◼ A company with advanced value- add expertise, a lean organizational structure, and high profitability ◼ Made the company a wholly owned subsidiary on Mar 6, 2025, to reinforce value-add operations and grow the pipeline Consolidation of Raysum (Announced in Sep. 2024) Achievements in FY2024 Consolidation of Koken Boring Machine Co., Ltd. (Announced in Jun. 2025 / Approx. 5.5 bn acquisition size) Real estate Child education Industrial Infrastructure Tender offer for Canadian Solar Infrastructure Fund, Inc. [TSE9284] (Announced in Jun. 2025 / Approx. 5.4 bn* acquisition size)Environment ◼ Acquired 84.69% of voting rights through a tender offer, making the company a consolidated subsidiary on Aug. 5 ◼ Made the company a wholly owned subsidiary on Nov. 19 ◼ Sponsored by one of the world's leading solar panel manufacturers. Listed in 2017. Holds a top-level asset scale among Japanese infrastructure funds. ◼ Entered into a support agreement, etc. with Canadian Solar Group and initiated business collaboration in solar power plants and grid-scale battery storage * Plan to acquire additional 25,804 units (6.01%) to make the company an equity- method affiliate, with total holdings of 20.0% Consolidation of Cook Deli, Inc. (Announced in Oct. 2025) Elderly Care (Healthcare) ◼ Entering the ready-to-eat meal business—an area expected to see further growth—as a solution that supports efficiency and labor shortage in the nursing care industry ◼ Acquired 51% of shares to make it a consolidated subsidiary. Leveraging our senior living operator network to accelerate further growth
Page 35
35 オペレーター Entering the high-growth-potential ready-to-eat meal business, leveraging our network with senior living operators to support and accelerate further growth of Cook Deli Expanding profits on a consolidated basis④ Consolidation of “Cook Deli” Company Overview Growth Support Strategy Company name Cook Deli, Inc. Founded in September 2016 Status Private Business outline Provider of ready-to-eat meal catering to senior living throughout Japan Number of employees 150 Support further growth Elderly Care / Healthcare related Business An industry-leading portfolio of approx. 5,000 senior living units leased to top-tier operators Our extensive operator network Real Estate Business Intangible Assets ◼ Cook Deli specializes in production and sale of “ready-to-eat meals" that only require plating and defrosting, and provides approx. 200,000 meals daily to approx. 7,000 facilities nationwide ※As of Nov. 2025 Achieving high profit margins with an asset-light business model through a fabless production system ◼ We acquired 51% ownership from existing shareholders and support their business growth by leveraging our network with senior living operators as we own approx. 70 such facilities (5,000 units) ◼ A labor shortage in the nursing care industry in Japan is driving demand for ready-to-eat meals, and the market size is growing at 17% p.a.
Page 36
36 Achieved JPY1.6 bn OP , JPY1.1 bn above the initial forecast, offsetting higher opening costs. Performing well across all brands. FUFU Jogashimaopens in Feb. and GATE Osaka in Jun. Expanding profits on a consolidated basis⑤ Tourism-related Business Brand High-end Ryokans(FUFU) THE GATE HOTEL View Hotels Target For the wealthy For the upper-middle For the middle-classed Concept Top Luxury Ryokans (Japanese style resort inns), more than 50-100㎡ per room, every room has natural hot spring Brand concept is “To offer authentic value to our guests” Captured touristic demand (domestic and international) by spreading the charms of Japanese culture Current status Awarded at 7 facilities for two consecutive years Acquired 4 development sites Acquired 3 development sites in central Tokyo Established strategic management through sharing human resources, etc. withTHE GATE HOTEL Asakusa View Hotel Asakusa Rokku Development pipeline As of the end of 2025 Opening year 2026 2027 onward # of facilities # of rooms # of facilities # of facilities High-end Ryokan (FUFU) 12 302 1 Jogashima Secure 4 sites (e.g., Kyu-Karuizawa) THE GATE HOTEL 7 1,062 1 Osaka Secured 3 sites (e.g., Ginza) *MICHELIN Key: A MICHELIN Guide’s selection for hospitality venues, comparable to the 'Star' for restaurants. THE GATE HOTEL Sapporo (Open on Dec. 20, 2025) FUFU Tokyo Ginza (Open on Nov. 16, 2025) FUFU Jogashima (Open on Feb. 27, 2026) THE GATE HOTEL Osaka (Open on Jun. 15, 2026)
Page 37
37 FUFU Jogashima is set to open in Feb. as the first all-ocean-view FUFU, with bookings on track. THE GATE HOTEL Osaka, the Kansai flagship, is opening in Jun. Expanding profits on a consolidated basis⑤ Tourism-related Business (Newly Opening Hotel and Ryokan) Address 693 Jogashima, Misaki-machi, Miura- shi, Kanagawa # of floors 4F Completion Nov. 2025 Open on Feb. 27, 2026 FUFU Jogashima Melody of the Sea Breeze Address 3-12-14 Minamisemba, Chuo-ku, Osaka-shi, Osaka # of floors 28F / B2 (Hotel: 16F-28F) Completion Mar. 2026 Open on Jun. 15, 2026 • Direct access to Shinsaibashi Station; about 15 minutes from Shin-Osaka Station • 223 rooms across 6 types — the largest count in the brand • Features include “Anchor Osaka” restaurant with a 26th-floor atrium, a 28th-floor rooftop bar with city views, and an exclusive guest lounge Rooftop bar “PEAKS” Guest room “THE GATE” Guest room ”LUXE” THE GATE HOTEL Osaka by HULIC Guest room Guest roomPrivate hot spring Guest room • About 2 hours from central Tokyo by train/bus, or 90 minutes by car • All 34 rooms (58–140㎡, 7 types) feature natural hot-spring baths with ocean views • Restaurant offers seasonal, seafood-focused Japanese cuisine with ocean breezes
Page 38
38 Jointly develop and operate "WING NRT," Japan's first integrated bonded warehouse and logistics facility with Japan Airlines Initiatives for “Hulic in the next 10 years”① Narita Logistics Development Project Narita Logistics Development Project 「WING NRT」 Project Plan Address Shimo-fukuda area, Narita-shi, Chiba Land Approx. 450,000㎡ *Acquisition completed Total floor Approx. 420,000㎡ (a total of all facilities) Incl. Approx. 150,000㎡ (bonded warehouse zone) Access 10 min drive from NRT *after the extension of North Chiba Highway (currently 15 min) Completion 2029 Convenient location to NRT International Airport *The image is based on current plan and is subject to change ◼ 10 min drive from NRT, after the extension of North Chiba Highway ◼ Responding to estimated growth in international cargo demandwith Narita Airport’s Runway C launch in March 2029 ◼ Japan Airlines will use the bonded warehouse facility, featuring advanced technologies and equipment including temperature-controlled pharmaceutical storage and cold storage units, etc. to provide high value-added services ◼ Collaborating with Japan Airlines on exploring post-opening facility operations and tenant leasing activities Features: ✓ An international logistics hub integrating bonded shed and logistics facilities ✓ Customs and quarantine services will be stationed (plan), provides extra efficiency and convenience ✓ Creating jobs for locals ✓ Function as a disaster response base Shared Use Fac. Logistics Fac. Logistics Fac. Bonded Warehouse Fac. Management Fac. *Worldwide-cargo Innovation Gate Narita
Page 39
39 Initiatives for “Hulic in the next 10 years”② Sports & Entertainment Business Announced arena development at Makuhari Kaihin Park (Chiba), targeting 2030 opening and profit generation through operations and services (tentative name) Makuhari Arena Development Project ◼ Developing a 20,000-seat arena, meeting global standards ◼ The arena will serve as Altiri Chiba’s home arena, and it is planned to host various domestic and international entertainment events ◼ Pursuing business profits through operations and services as part of expanding into the sports and entertainment business ◼ Aiming for 2030 opening Project Plan Address 1-110 Hibino, Mihama-ku, Chiba-shi, Chiba Access 3 min walk from Kaihin Makuhari Station, JR Keiyo Line 3 min by car from Wangan Chiba IC Land Approx. 50,000㎡ Total floor Approx. 54,000㎡ # of floors 6F Arena capacity 20,000 people About Altiri Chiba [professional basketball club] *The image is based on current plan and is subject to change • Founded in 2020 and promoted to B2 in its first B3 season • Achieved the league’s fastest-ever promotion, winning B2 and advanced to B1. Set to join the new B.Premier (current B1) launching in 2026 • Strong fan engagement, with B2 home-game attendance above the B1 average and further growth this season Jan 2025: formed a capital alliance and entered into a sponsorship agreement with Altiri Co., Ltd., which manages the professional basketball club "Altiri Chiba,” based in Chiba City
Page 40
40 Started initiatives for monetarizing renewable energy business and new domains such as luxury senior residence. Making strategic investments in view of the next long-term plan Initiatives for “Hulic in the next 10 years”③ Others Grid-scale power storage facilities ◼ Invest JPY100.0 bn by 2034 in anticipation of growing demand for grid-scale power storage facilities in response with power fluctuations ◼ Aim to capture new earnings sources by trading electricity in the electricity market and with retail electricity providers ◼ Centralized renewable energy businesses to a new company ‘Hulic Energy Solution Co., Ltd.’ Luxury senior residence ◼ Develop and manage residences for active seniors to meet the growing needs of high-net-worth individuals ◼ New businesses that combine “the elderly and health care”, “tourism”, and “membership business” areas where Hulic has expertise ◼ Collaborate with industry’s top companies with extensive experience Capital and business alliance with ASTMAX Co., Ltd. Example 1 Example 2 Grid-scale battery storage facility ◼ In Jun. 2025, our consolidated subsidiary Hulic Property Solution Co., Ltd. acquired shares of Astmax Co., Ltd., turning it into an equity-method affiliate (18.04% of total voting rights) ◼ Contribute to monetarization of renewable energy business through the capital and business alliance ASTMAX Co., Ltd. (Securities Code: 7162) • A general energy company • Specialized in retail electricity trading, handling power supply-demand management for our group • Experienced in renewable energy and power storage facility development/operation Aim of the alliance ◆Retail electricity business Expand our electricity business earnings and customer base by leveraging Astmax Group's expertise to optimize our retail electricity operations ◆Renewable energy & storage battery business Strengthen business foundation and expand earnings by acquiring battery development know-how through joint projects ◼ As of the end of 2025, two sites are operational (in Shizuoka and Chiba Pref.)
Page 41
41 Sustainability Initiatives
Page 42
42 Progressing steadily towards achieving 100% renewable energy buildings by 2029 Our first and second grid-scale power storage facilities began operation Sustainability: Environment ~2022 2023 2024 2025 ~2029 2030 ~2050 General Recycling- oriented Society & Decarbon -ization GHG Reduction Targets*² Scope1+2 ●Reduce by 70%*3 Scope3 ●Reduce by 30%*3 ✓ Started disclosing information in line with TCFDs ✓ Disclosed SBT-approved GHG emissions reduction targets Adoption of environmentally friendly technologies to properties owned Achieve by 2029 Plan to achieve 1 year ahead of ongoing plan RE100RE100 Achieved in 2023 In response to lease assets (downstream) Aim to offer buildings that are chosen by tenants from environmental friendliness Will reduce GHG emissions by 132,000t-CO2e which is equivalent to 78,000 household annual emissions Powering all company-owned buildings*1 with 100% in-house renewable electricity Achieved 2 years ahead of initial plan Substantially Zero by 2050 Initiatives for buildingsInvestment in renewable power plant Small hydroelectric plant [FIT] (Shiga Pref.) Solar power plant equipped with battery storage [non-FIT] (Tochigi Pref.) Newly development Acquisition Development of ZEB (Zero Energy Buildings) Ensure exceptional environmental measures for the purpose of promoting decarbonization in development project ZEB : Hulic Logistics Series (Noda I, Kashiwa, Hashimoto, Noda II, Misato) Promoting use of wood Use of eco-friendly materials Use eco-friendly concreate and asphalt to reduce embodied carbon (Scope 3 upstream emissions) *1: Excludes single-tenant lease properties, residential properties and unmanaged shared properties for which we do not manage energy, and real estate for sale. *2: base year: 2019 *3: SBT-approved near-term targets. Combined Scope1+2 targets are consistent with reductions required to keep the global warming to 1.5℃, the most ambitious goal of the Paris Agreement. Scope3 target meets the SBTi’s criteria for ambitious value chain goals, meaning they are in line with current best practice. Wind power plant [FIT] (Akita Pref.) Grid-scale power storage facility Plan to invest JPY100.0 bn by 2034 in grid-scale power storage facilities ✓ Started disclosing information in line with TNFDs
Page 43
43 High level of property safety standards Focus on earthquake and disaster contingency planning Sustainability: Social Stricter in-house standards than the Building Standard Act and our buildings can withstand a seismic intensity of 7 level ✓ Achieved 100% highly quake-resistant buildings (excl. those to be reconstructed or sold, etc.) in our leasing portfolio as of the end of 2025 ✓ Promote introduction of “Sokushin Navi”, a new damage assessment system, to non-current assets ✓ Active use of Earthquake-Absorbing / Damping Structure ✓ Confirmed all properties located in Nankai Trough Earthquake Disaster Prevention Promotion Area have seismic performance that can withstand intensity level 7 earthquakes (Japanese scale) (as of Aug. 2024) ✓ Measures against flooding of electrical equipment in owned buildings Installation of tide barriers and simple water stop boards Roof drain cap Vertical damp proof barrier Measures against huge earthquakes Measures against Mt. Fuji volcanic ashes Flood control measures Safe and Secure Buildings Human Capital Initiatives 6% base salary increase for 2026 has been finalized (excl. regular pay raises). Starting salaries have also been increased to the highest among peers: JPY330,000 (BA), JPY370,000 (MA) *Salary increase rates are calculated excluding managing officers and fixed-term employees ✓ Ratio of female among directors and auditors: 33%*¹ ✓ Female employee birth rate 1.94*² (Japan average: 1.20*²) ✓ Rate of female employee returning to work following child leave: 100% ✓ Usage rate of parental leave: male 100%, female 100% ✓ Introduced selective four-day workweek system ✓ Eligibility for family leave and shortened work hours are extended to grade 6 ✓ Paid leave usage rate: 81.2% ✓ Chosen by the Government as Certified Health and Productivity Management Organization for consecutive 7 years Improving work motivation Empowering women Maintaining decent work environment Social Contributions Support for Shogi culture ✓ Strengthened support by increasing prize money for two co-hosted/ specially sponsored tournaments ✓ Awarded “Medal with Dark Blue Ribbon” Other social contributions ✓ Supporting Japan Service Dog Association Support Shogi Culture (Female Competition) ✓ Hardware measures Development and introduction of a system to prevent volcanic ash from intrusion into stormwater drains ✓ Measures for both hardware and software Establishment of systems and deployment of equipment for rapid recovery work Unless otherwise noted, all figures on this page are based on 2025 results *1: As of Jun. 30, 2025 *2: Total fertility rates (Recent 3-year average) Hulic Shogi-Kaikan Sendagaya Building ► Highly productive organization Ordinary profit per employee: JPY660 mil
Page 44
44 Transparent governance framework established; Majority of BOD are independent external directors. Rated highest for MSCI ESG ratings and CDP Climate Change Sustainability: Governance / External Evaluation Board of Directors ✓ Nominating Committee and Remuneration Committee all members are independent external directors ✓ Majority of members (6 out of 10) are independent external directors ✓ External director serves as the chairperson Audit & Supervisory Board ✓ Majority of members (3 out of 5) are independent external auditors Establishment of discretionary committees D&I among Board Members ✓ Ratio of female among directors and auditors: 33%*1 ✓ Appoint three female directors and two female auditors Introduction of stock compensation ✓ Director remuneration consists of a basic fee and performance-based fee which includes stock compensation to reflect a medium- to long-term perspective ✓ Clawback mechanism is in place *1: Ratio of female among directors and auditors Corporate Governance External Evaluation HULIC is a constituent of all 6 domestic ESG indices adopted by GPIF Our GHG emissions reduction targets are approved by SBTi Rated AAA grade in MSCI ESG ratings ESG investment indices Received “Platinum Kurumin” Selected for the 2024 Climate Change “A” List by CDP Rated 4.5 stars in Nikkei SDGs Management Survey
Page 45
45 Appendix
Page 46
46 Macro Environment Office Market / Inbound Spending Trends ◆ Supply is estimated to remain on par with the past decade over the next five years Supply Volume of Large-scale Tokyo Office Building Source: Mori Building Co., Ltd. Market trend Survey of Large-Scale Office Buildings in Tokyo’s 23 wards (Updated May 22, 2025) Top 5 wards: Chiyoda, Chuo, Minato, Shinjuku, Shibuya (1,000㎡) 1,190 750 1,440 510 360 1,180 340 1,040 760 380 650 1,130 220 100 350 100 120 70 80 280 140 70 0 140 1,410 850 1,790 610 480 1,250 430 1,320 900 450 650 1,270 0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 Top 5 wards Other 18 wards Research target : GFA more than 10,000㎡ Source: Japan Tourism Agency (Jan. 21, 2026) ◆ Travel spending by foreign visitors in 2025 reached a record-high Trend in Travel Spending by Foreign Visitors 4,416 4,519 4,814 745 121 899 5,307 8,126 9,455 154 153 159 185 235 213 227 229 0 100 200 300 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 2017 2018 2019 2020 2021 2022 2023 2024 2025 Travel expenditure by foreign visitors (Left axis) Travel expenditure per person (Right axis)(Billion yen) (Thousand yen) Estimated
Page 47
47 Portfolio restructuring underway: achieved 100% quake-resistant buildings (excl. those to be sold or reconstructed, etc.) and 50% in focus areas. Maintain office ratio at 50% or below Previous Medium-Term Management Plan (2025-2027) Progress of Leasing Portfolio Restructuring KPI Plan Progress Assets in Focus Areas 50%*3 ◼ Strictly selected locations ◼ Focus on Tokyo central (Ginza, Shinjuku east, Shibuya/Aoyama, Asakusa) 2019 end 2025 end 2029 Office share Less than 50%*³ ◼ Establish a balanced asset class composition with the ratio of office buildings at 50% at a maximum ◼ In response to a decline in working population, promote more to develop and acquire commercial and next generation assets, etc. 2025 end2019 end 2029 100% highly earthquake resistant buildings*¹ ◼ Response to tenants’ BCP needs for future disasters (earthquakes, Mt. Fuji eruption) ◼ Achieved 100% (excl. those to be reconstructed or sold, etc.) as of the end of 2025 2025 20292024 end Achieved 100% excluding those to be sold or reconstructed, etc. 100% renewable energy buildings*² ◼ 100% renewable energy for our business operations and all company-owned buildings*² ◼ Aim to achieve the target by 2029 through investing and developing renewable energy facilities in-house 2029 *1: Property number basis. Highly earthquake resistant buildings are those that can safeguard human life and enable continued u se of the building with post-earthquake repairs when an earthquake occurs with a seismic intensity of 7 level. Excluding those to be sold *2: Property number basis. Excludes properties for which we do not have energy management authority including master lease prop erties, residential properties and non-managerial co-ownership properties, and real estate for sale *3: Office share: Rent revenue basis, Assets in Focus Areas: Book value basis Leasing Portfolio chosen by tenants and society Higher rent Low vacancy Competitive advantages 86% 100% 100% 63% 46% 50% 50%43% Achieved RE100 in May 2023 2 years ahead of initial plan (Initial plan: 2025) Less than 50%
Page 48
48 Financial Summary FY2025 Consolidated Cash Flow Statements (Million yen) FY2024 FY2025 Change Cash flows from operating activities 353,388 269,239 -84,149 Cash flows from investing activities -602,020 -544,500 57,519 Free cash flow -248,631 -275,261 -26,629 Cash flows from financing activities 300,589 272,264 -28,324 Cash and cash equivalents at end of period 134,326 130,655 -3,671 Major factors for changes Real estate investment +48.0 bn (incl. investments in M&A/SPCs, etc.) Decrease (increase) in real estate for sale, etc. -94.6 bn Income taxes paid -15.1 bn Profit before income taxes +20.2 bn Raysum M&A financing in FY24 -173.5 bn Proceeds from bond issuance and long- term borrowings* +354.8 bn Bond redemption and long-term borrowing repayments -271.5 bn Proceeds from CP issuance +60.0 bn *Excludes the portion refinanced to long-term borrowing from Raysum M&A bridge loan
Page 49
49 0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 0 200 400 600 800 1,000 1,200 1,400 08/11 10/03 11/07 12/11 14/03 15/07 16/11 18/03 19/07 20/11 22/03 23/07 24/11 Market Cap 3625 Former HULIC (Right axis) 3003 New HULIC (Right axis) Corporate Profile Market Capitalization, Stock Price Market Capitalization & Stock Price (weekly) History (Nov.14, 2008~Dec. 30, 2025) Market Capitalization (upper row) and Stock Price (period-end closing price) (lower row) ( Billion yen ) (yen) 2008_end 2009_end 2010_end 2011_end 2012_end 2013_end 2014_end 2015_end 2016_end 2017_end 2018_ end 2019_end 2020_end 2021_end 2022_end 2023_end 2024_end 2025_end 60.0 bn 87.5 bn 115.0 bn 154.1 bn 346.3 bn 926.3 bn 722.0 bn 708.2 bn 688.7 bn 839.4 bn 653.1 bn 886.9 bn 763.5 bn 838.6 bn 798.6 bn 1,133.8 bn 1,052.0 bn 1,316.6 bn 410 Yen 598 Yen 670 Yen 898 Yen 583 Yen 1,555 Yen 1,211 Yen 1,069 Yen 1,039 Yen 1,266 Yen 985 Yen 1,316 Yen 1,133 Yen 1,092 Yen 1,040 Yen 1,477 Yen 1,370 Yen 1,715 Yen Note: In consideration of the July 1, 2012 merger with Shoei Co., Ltd. (share exchange ratio: former Shoei : former Hulic = 1 :3), the stock prices recorded up until the end of December 2011 refer to the former Hulic, while prices recorded from the end of December 2012 onward refer to the new Hulic. Great East Earthquake Shoei merger announcement (merger ratio 3:1) JPX Nikkei Index 300(Aug. 2014) P.O. JPX Nikkei Index 300(Mar. 2017) TOPIX P.O. Covid-19 Pandemic P.O. 11/12 14/12 17/12 20/12 22/1209/12 10/12 13/1212/12 15/12 16/12 18/12 19/12 21/12 23/12 24/1208/12 25/12
Page 50
50 Corporate Profile Major Shareholders (Top 10) Company name As of the end of Dec. 2025* 1. The Master Trust Bank of Japan, Ltd. (Trust account) 10.85% 2. Meiji Yasuda Life Insurance Company 6.21% 3. Fuyo General Lease Co., Ltd 5.30% 4. Yasuda Real Estate Co., Ltd 4.01% 5. Custody Bank of Japan, Ltd. (Trust account) 3.74% 6. Yasuda Logistics Corporation 3.70% 7. Oki Electric Industry Company 3.34% 8. Mizuho Capital Co., Ltd 3.33% 9. Tokyo Tatemono Co., Ltd 2.65% 10. TEIKOKU SEN-I Co., Ltd 2.21% Total 45.34% Non-Japanese ownership 18.91% Individual ownership 15.14% *Shareholding ratios for Major Shareholders are calculated by excluding treasury stocks
Page 51
51 Corporate Profile Hulic’s Asset Information (Senior Living) Hulic property Name Address Date Rooms 1 Iris garden Kita-Urawa Saitama-shi, Saitama 2010 48 2 Aristage Kyodo Setagaya-ku, Tokyo 2012 146 3 Charm Suite Nishinomiyahama Nishinomiya-shi, Hyogo 2015 50 4 Lianreve Yakumo Meguro-ku, Tokyo 41 5 Life Commune Hayama Miura-gun, Kanagawa 2016 48 6 Life Commune Tsutsujigaoka Mitaka-shi, Tokyo 101 7 Medical Home Granda Okamoto Kobe-shi, Hyogo 2017 67 8 Charm Premier Fukasawa Setagaya-ku, Tokyo 85 9 Sompo no ie Komae Komae-shi, Tokyo 2018 33 10 Asheim Oizumigakuen Nerima-ku, Tokyo 50 11 Fukagawa Yasuragi no sono Koto-ku, Tokyo 69 12 Charm Premier Yoyogi Hatsudai Shibuya-ku, Tokyo 36 13 Trustgarden Ogikubo Suginami-ku, Tokyo 2019 51 14 Good care Nishi Tokyo Nishi Tokyo-shi, Tokyo 52 15 Medical Rehabilitation Madoka Omiya Saitama-shi, Saitama 58 16 Charm Premier Eifuku Suginami-ku, Tokyo 48 17 Charm Premier Meguro Kakinokizaka Meguro-ku, Tokyo 37 18 Charm Premier Grand Shoto Shibuya-ku, Tokyo 2020 36 19 Tsukui Sunshine Seijyo Setagaya-ku, Tokyo 121 20 Rehabilitation Home Granda Kugenuma Fujisawa (Land) Fujisawa-shi, Kanagawa 46 21 Charm Premier Grand Minami-Azabu Minato-ku, Tokyo 2021 32 22 Hospitalment Yotsuya Daikyocho Shinjuku-ku, Tokyo 61 23 Aria Tetsugakudo Nakano-ku, Tokyo 43 24 Good time Living Shin-Urayasu Urayasu-shi, Chiba 76 25 Hospitalment Aoyama Shibuya-ku, Tokyo 2022 53 26 Sonare Meguro Fudō-mae Meguro-ku, Tokyo 58 27 Plaisant Grand Kyoto Enmachi Kyoto-shi, Kyoto 80 28 Granda Tezukayama Osaka-shi, Osaka 45 29 Granda Tetsugakudo Koen Shinjuku-ku, Tokyo 57 30 Good Time Nursing Home Higashi Kojiya Ota-ku, Tokyo 2023 45 31 Charm Suite Yotsuya Shinjuku-ku, Tokyo 67 32 Asheim Mitaka Mitaka-shi, Tokyo 93 33 Charm Premier Gotenyama Sanbankan Shinagawa-ku, Tokyo 60 34 SOMPO Care La vie re Grand Syukugawa Nishinomiya-shi, Hyogo 62 35 Sawayaka Mejiro no sato Shinjuku-ku, Tokyo 56 36 Charm Premier Grand Ikedayama Shinagawa-ku, Tokyo 2024 30 37 Hospitalment Bunkyo Gran Bunkyo-ku, Tokyo 67 38 Bon Séjour Nishikokubunji Kokubunji-shi, Tokyo 55 39 L’Aubel Nakano Saginomiya Nakano-ku, Tokyo 79 40 Plaisant Grand Seijo Setagaya-ku, Tokyo 2025 79 41 Plaisant Grand Senzoku Shinagawa-ku, Tokyo 49 Total Rooms 4,908 Under development Name Address Date Rooms 1 Senior living in Benten-cho Shinjuku-ku, Tokyo 2027 (plan) 47 (plan) 2 Azabu F Building Reconstruction ProjectMinato-ku, Tokyo 55 (plan) 3 Senior living in Sendagaya Shibuya-ku, Tokyo 45 (plan) To Hulic Group (REIT) Name Address Date Rooms 1 Aria Matsubara Setagaya-ku, Tokyo 2016 96 2 Trustgarden Sakurashinmachi Setagaya-ku, Tokyo 86 3 Trustgarden Yoga no mori Setagaya-ku, Tokyo 129 4 Trustgarden Suginami-miyamae Suginami-ku, Tokyo 100 5 Trustgarden Tokiwamatsu Shibuya-ku, Tokyo 50 6 SOMPO care Lavier Kita Kamakura Kamakura-shi, Kanagawa 2017 98 7 Sunnylife Tokyo Shinjuku Shinjuku-ku, Tokyo 2018 141 8 Hospitalment Itabashi Tokiwadai Itabashi-ku, Tokyo 92 9 Toyosu Senior Residence Koto-ku, Tokyo 2019 186 10 Charm Suite Shakujii Park Nerima-ku, Tokyo 105 11 Charm Suite Shinjuku Toyama Shinjuku-ku, Tokyo 90 12 Hospitalment Musashino Musashino-shi, Tokyo 2020 114 13 Charm Suite Chofu Chofu-shi, Tokyo 2021 84 14 Esperal Joto Osaka-shi, Osaka 286 15 Nichii Home Moto Sumiyoshi Kawasaki-shi, Kanagawa 52 16 Granda Omori Sanno Ota-ku, Tokyo 70 17 Asakusa Care Park Soyokaze Taito-ku, Tokyo 2022 41 18 Good time Home Tamagawa Ota-ku, Tokyo 41 19 Granda Gakugeidaigaku Meguro-ku, Tokyo 70 20 Hospitalment Hongo Bunkyo-ku, Tokyo 2023 46 21 Charm Premier Den-en-chofu Setagaya-ku, Tokyo 40 22 Sonare Shakujii Nerima-ku, Tokyo 52 23 Aria Yoyogi Uehara Shibuya-ku, Tokyo 2024 40 24 Kamakura Aoi tei Kamakura-shi, Kanagawa 26 25 Charm Premier Yamatecho Yokohama-shi, Kanagawa 36 *High-class Assisted Living type. Hulic (landowner) does NO operation. Properties scheduled to be acquired Name Address Date Rooms 1-2 2 senior living - 2026-27 (plan) 120 (plan) Note: Number of rooms are counted at the time of property acquisition or completion
Page 52
52 Corporate Profile Hulic’s Asset Information (Hotels and Japanese Ryokans) THE GATE HOTEL (operated by HULIC Group) Name Open Rooms 1 THE GATE HOTEL Kaminarimon*¹ 2012 134 2 THE GATE HOTEL Tokyo 2018 164 3 THE GATE HOTEL Kyoto Takasegawa 2020 184 4 THE GATE HOTEL Ryogoku 126 5 THE GATE HOTEL Yokohama*1 2025 111 6 THE GATE HOTEL Fukuoka 171 7 THE GATE HOTEL Sapporo 172 8 THE GATE HOTEL Osaka 2026 (plan) 223 9 Ginza 7-chome Showa St. Development Project New 2029 (plan) - Total 1,285 Luxury inn Ryokan (managed by HULIC Group) Name Acquisition / Open Rooms 1 Hakone Suishoen 2015 23 2 FUFU ATAMI 26 3 ATAMI Kaihoro 2016 4 4 FUFU KAWAGUCHIKO (Mt.Fuji) 2018 32 5 FUFU NARA 2020 30 6 FUFU NIKKO 24 7 FUFU ATAMI Annex 2021 6 8 FUFU KYOTO 40 9 FUFU HAKONE 2022 39 10 FUFU Karuizawa 2023 24 11 FUFU Kyu-Karuizawa 20 12 FUFU Tokyo Ginza 2025 34 13 FUFU Jogashima 2026 (plan) 34 14 FUFU Kyu-Karuizawa Annex New 2028 (plan) - Total 336 View Hotel (operated by HULIC Group) Name Acquisition / Open Rooms 1 Asakusa View Hotel*1 2019 326 2 Ryogoku View Hotel 150 3 Osaka View Hotel Honcho 170 4 Sapporo View Hotel Odori Park 347 5 Asakusa View Hotel Annex Rokku 2023 199 6 Maihama View Hotel 2025 428 Total 1,620 Hotel Investments (Master-leasing) Name Acquisition / Open Rooms 1 Sotetsu Fresa Inn Tokyo Roppongi (shared) 2016 201 2 Sotetsu Fresa Inn Ginza (to REIT) 286 3 New-Ohtani Inn Yokohama premium 2017 240 4 Ginza Capital Hotel Moegi (to REIT) 2018 136 5 The Royal Park Hotel Ginza 6-chome 2024 273 Total 1,136 Total 5,334 Other Hotels (operated by HULIC Group) Name Acquisition / Open Rooms 1 Grand Nikko Tokyo Bay Maihama (to REIT) 2014 703 2 Hotel Nikko Kanazawa 2018 254 Total 957 *1: Properties owned by Hulic’s REITs or funds *2: Tokyo Bay Maihama Hotel has been rebranded as Maihama View Hotel on Oct. 1, 2025
Page 53
53 Corporate Profile Hulic’s Asset Information (Major Hotels and Japanese Ryokans) THE GATE HOTEL Kyoto Takasegawa THE GATE HOTEL Ryogoku THE GATE HOTEL Kaminarimon THE GATE HOTEL Tokyo PPP project FUFU Karuizawa FUFU Kyu-Karuizawa PPP project *Owned by Hulic’s REITs or funds FUFU Hakone FUFU Nikko FUFU Nara FUFU KawaguchikoPPP project FUFU Kyoto Seven FUFU facilities were selected as for two consecutive years THE GATE HOTEL Yokohama Opened in 2025 *Owned by Hulic’s REITs or funds THE GATE HOTEL Fukuoka THE GATE HOTEL Sapporo Opened in 2025 FUFU Tokyo Ginza Opened in 2025 Major projects to be opened Shinsaibashi, Osaka (Open in Jun. 2026) Ginza (Open in 2029) Jogashima (Open in Feb. 2026) Major projects to be opened Opened in 2025
Page 54
54 Two THE GATE HOTEL opened in Yokohama (Feb.) and in Fukuoka (Apr.) in 2025 Recording favorable performance both in ADR and occupancy rate Corporate Profile Hulic’s Asset Information (Newly Opened Hotels) Address 11-3, Yamashita-cho, Naka-ku, Yokohama-shi, Kanagawa # of floors 13F Completion Nov. 2024 Address 2-8-49, Tenjin, Chuo-ku, Fukuoka-shi, Fukuoka # of floors 19F / B3 (Hotel: 10-19F) Completion Dec. 2024 Guest room “THE GATE” Restaurant “Anchor Grill Yokohama” Rooftop Terrace • 111 refined rooms in 5 types, overlooking Yokohama Bay and Yamashita Park • Art Deco-inspired interiors with modern art accents, evoking Yokohama’s heritage • Domestic demand is stronger compared to other GATE HOTEL locations. ADR has been exceeding our initial plans Opened on Feb. 26, 2025 Opened on Apr. 24, 2025 Guest room “Essential” Guest room “Classy”Anchor Grill Fukuoka Lobby Lounge (terrace area) THE GATE HOTEL Fukuoka by HULIC THE GATE HOTEL Yokohama by HULIC • Located on 10th to 19th floors of HULIC SQUARE FUKUOKA TENJIN • Main room types "Classy" and "Essential" offer a spacious, functional, and relaxing stay • Terrace seating available at the Lobby Lounge on the top (19th) floor • The guest-exclusive lounge is especially well-received by guests. ADR has been exceeding our initial plans
Page 55
55 THE GATE HOTEL Sapporo opened in Dec. 2025 with a smooth start Construction began for Ginza 7-chome Showa St. in Nov. 2025 Corporate Profile Hulic’s Asset Information (Newly Opening Hotels) • Direct to “Sapporo” subway station. Located on 11th to 20th floors of HULIC SQUARE SAPPORO II • 172 rooms in 6 types, covering various needs from business to family stays • Facilities include all-day dining on the 10th floor, an exclusive guest lounge on the top floor, and a large public bath Open on Dec. 20, 2025 Guest room “Luxe”Large public bath Guest room “THE GATE” Guest-exclusive lounge Address 7-13-10 Ginza, Chuo-ku, Tokyo # of floors 15F / B1 Completion 2029 Complete in 2029 • Targeting inbound families and group travelers • Planning connecting rooms and rooms for multiple guests to support diverse stay styles • Top-floor guest-exclusive lounge and restaurant offer an open space with large windows and terraces overlooking Ginza Guest room (image) Guest-exclusive lounge and restaurant (image) Entrance (image) Ginza 7-chome Showa St. Development Project THE GATE HOTEL Sapporo by HULIC Address 3-1-44 Kitasanjo Nishi, Chuo-ku, Sapporo-shi, Hokkaido # of floors 20F / B1 (Hotel: 11-20F) Completion Sep. 2025
Page 56
56 Corporate Profile Hulic’s Asset Information (Major retail facilities) HULIC &New GINZA 8 (Chuo-ku, Tokyo) HULIC &New SHINJUKU (Shinjuku-ku, Tokyo) HULIC &New GINZA NAMIKI 6 (Chuo-ku, Tokyo) HULIC &New KICHIJOJI (Musashino-shi, Tokyo) HULIC &New Series • Series concept “Bringing new added value to daily living” • Developing “commercial buildings with a strong presence” under “&New” series of medium-sized urban- style commercial facilities • 12 facilities at present, 2 more are under planning Tokyo Prime Area Value Added Projects LICOPA Tsurumi (Former Ito Yokado Tsurumi) World Town Building Renovation Project Tiffany Ginza Building Hulic Ginza Sukiyabashi Building • Invest in assets with added-value potential • Promote Ito Yokado store total renovation projects in Tokyo suburbs • Leasing to global luxury brand flagship stores in top commercial district: Ginza, Shibuya, Aoyama, Shinjuku, etc. LICOPA Kawasaki (Former Ito Yokado Kawasaki parking space) HULIC &New GINZA 7 (Chuo-ku, Tokyo) Ginza 5-chome Development Plan Under demolition One’s Mall (Chiba-shi, Chiba) Renovated and reopened in Sep. 2025
Page 57
57 Japan’s top commercial area, attracting global visitors. Luxury brands continue to show strong demand for opening stores. “FUFU” opened in Nov. 2025 Corporate Profile Hulic’s Asset Information (Recent Openings in Ginza Area) Hulic Ginza Sukiyabashi BuildingHulic Ginza Building 7-12F High-end Ryokan 3-6F Office B1-2F Retail Address 1-7-10 Ginza, Chuo-ku, Tokyo Access Direct to “Ginza 1-chome” Station, Tokyo Metro Line Total floor area 12,840.43㎡ Completion Aug. 2025 Address 4-2-11 Ginza, Chuo-ku, Tokyo Access 1 min walk from “Ginza” Station, Tokyo Metro Line Total floor area 11,569.86㎡ Completion Mar. 2011 34 rooms in 6 types, each with natural hot spring from Atami FUFU Tokyo Ginza (Open on Nov. 16, 2025) B1-B3 / 5-11F Office 1-4F Retail Mizuho Bank, etc. Cartier (Open in Sep. 2025) One of the largest flagship stores in AsiaHarry Winston (Open in Aug. 2025) • Located near Sukiyabashi Crossing, 1-min walk from "Ginza" Station and 4 min from JR "Yurakucho" Station, offering excellent convenience and visibility • Cartier opened Asia's largest flagship store after approx. 20 months of interior and exterior renovations upon eviction of the prev. tenant • Located at a corner facing three major streets (Chuo St./Yanagi St./Gaslamp St.) with excellent visibility • Opened 'FUFU' in Tokyo Ginza, aiming to further boost brand recognition among inbound visitors Van Cleef & Arpels (Open in Oct. 2025)
Page 58
58 Corporate Profile Hulic’s Asset Information (Logistics Center / Hulic Logistics Series) Misato was completed in Jul. 2025 Halted new development due to rising construction costs Name Location Total floor (Approx.) Completion 1 Hulic Logistics Kasai <Leased up> Edogawa-ku, Tokyo 19,923㎡ May 2022 2 Hulic Logistics Noda I <Leased up> Noda-shi, Chiba 34,352㎡ Nov. 2023 3 Hulic Logistics Kashiwa <Leased up> Kashiwa-shi, Chiba 20,677㎡ Dec. 2023 4 Hulic Logistics Hashimoto Sagamihara-shi, Kanagawa 62,797㎡ Jul. 2024 5 Hulic Logistics Noda II <Leased up> Noda-shi, Chiba 16,694㎡ Feb. 2025 6 Hulic Logistics Misato Misato-shi, Saitama 56,884㎡ Jul. 2025 5 4 3 2 1Tokyo Kanagawa Chiba Saitama Route 16 6 3 4 5 6
Page 59
59 Corporate Profile Ginza & Yurakucho Area Town Map Hulic owns 39 properties in Ginza, Yurakucho area (top retails) 1. Hulic Ginza Building 2. Nishi Ginza Development Project 3. Ginza Nishi 2-chome Parking Development Project 4. Hulic Ginza 1-chome Gas Lamp St. Building 5. Hulic Ginza 1-chome Building (Reit) 6. Hulic Ginza 2-chome Building 7. Hulic Ginza Sukiyabashi Building 8. HULIC SQUARE TOKYO 9. Hulic Ginza World Town Building 10. Hulic Ginza Wall Building 11. Hulic Ginza 7-chome Building 12. Hulic Ginza 3-chome Building 13. Hulic Ginza 6-chome Building 14. Hulic Ginza Hanatsubaki St. Building (Reit) 15. HULIC &New GINZA NAMIKI 6 16. HULIC &New GINZA 8 17. Hulic Ginza 6-chome Showa St. Building 18. Hulic Ginza East Building (Reit) 19. Ginza 7-chome Showa St. Development Project 20. Hulic Ginza 5-chome Namiki St. 21. Ginza First Building (Unit ownership) 22. HULIC &New GINZA MIYUKI 5 23. Ginza 8-chome 9-11,12 Development Project 24. HULIC &New GINZA 7 25. Tiffany Ginza Building 26. G8 Development Project 27. Ginza 6-chome Miyuki St. Development Project 28. Ginza 5-chome Development Project 29. Kobiki-kan Ginza Building 30. ALBORE Ginza 31. Hulic Ginza 1-chome Showa St. Building 32. PUZZLE GINZA 33. Ginza 5-chome 3-9 Development Project 34. NREG Ginza Building 35-39. Not disclosed
Page 60
60 Corporate Profile Shinjuku East Area Town Map Hulic owns 7 properties in Shinjuku East district (commercial zone) 1. Hulic Shinjuku Building 2. HULIC &New SHINJUKU 3. Hulic Shinjuku 3-chome Building 4. Hulic Shinjuku Gyoen Building 5. Shinjuku 318 Development Project 6. FORECAST Shinjuku SOUTH 7. Not disclosed *partial ownership through an SPC investment
Page 61
61 Hulic owns 7 properties in Asakusa district (Old Town/tourist spot) Corporate Profile Asakusa Town Map 1. Hulic Kaminarimon Building (Reit) 2. HULIC &New Kaminarimon (Reit) 3. WINS Asakusa Building 4. Asakusa Park Hall Building 5. Hulic Asakusa 1-chome 6. Asakusa View Hotel (Reit) 7. Asakusa Care Park Soyokaze (Reit) Kappabashi Kappabashi Minami Kappabashi Minami
Page 62
62 Corporate Profile Shibuya & Aoyama Town Map Miyamasuzaka District Redevelopment Project Shibuya 1-chome Area Joint Development Project Hulic owns 28 properties in Shibuya, Aoyama area (commercial zone) 1. Hulic Shibuya Building 2. Hulic Shibuya Building #2 3. CR-Vite 4. Hulic Shibuya 2-chome Building 5. Hulic Shibuya Udagawacho Building* 6. HULIC &New SHIBUYA (Reit) 7. HULIC &New UDAGAWA II (Reit) 8. Shibuya Parco・Hulic Building (Office block) 9. Hulic Shibuya Park Avenue Building (Reit) 10. Hulic Shibuya Inokashira St. Building (Reit) 11. Aoyama Building Reconstruction Project 12. Hulic Jingumae Tower Building 13. Hospitalment Aoyama 14. Charm Premier Grand Shoto 15. Trustgarden Tokiwamatsu (Reit) 16. Hulic Shibuya 1-chome Building (Reit) 17. Shibuya 1-chome Development Project 18. Hulic Shibuya Mitake St. Building 19. YO Building (Reit) 20. Hulic Jingumae Building (Reit) 21. Harajuku Takeshita-dori Commercial Store (Land) 22. Omotesando Development Project I 23. Hulic Shibuya Miyamasuzaka Building 24, 25. Not disclosed *Hulic owns 3 more neighboring buildings
Page 63
63 Corporate Profile Advertisement Wow! It’s Hulic again. Building close to the future and station. Hulic for real estate Wow! It’s Hulic again. Building close to the future and station. Hulic for real estate We support people who challenge the future Building close to the future and station. Hulic for real estate Official Gold Partner of the Japan Para-Badminton Federation Hulic develops new power plants and generates its own renewable energy. 1st case in Japan Hulic makes society clean, safe and secure by providing tenants with renewable energy and highly earthquake resistant buildings Hulic Cup Hakurei Championships Shogi Competition for women
Page 64
64 Disclaimer on External Evaluations for Sustainability Initiatives. The inclusion of Hulic Co., Ltd. in any MSCI index, and the use of MSCI logos, trademarks, service marks or index names herein, do not constitute a sponsorship, endorsement or promotion of Hulic Co., Ltd. by MSCI or any of its affiliates. The MSCI indexes are the exclusive property of MSCI. MSCI and the MSCI index names and logos are trademarks or service marks of MSCI or its affiliates. FTSE Russell confirms that Hulic Co., Ltd. has been independently assessed according to the index criteria, and has satisfied the requirements to become a constituent of the FTSE JPX Blossom Japan Index. Created by the global index and data provider FTSE Russell, the FTSE JPX Blossom Japan Index is designed to measure the performance of companies demonstrating specific Environmental, Social and Governance (ESG) practices. The FTSE JPX Blossom Japan Index is used by a wide variety of market participants to create and assess responsible investment funds and other products. FTSE Russell confirms that Hulic Co., Ltd. has been independently assessed according to the index criteria, and has satisfied the requirements to become a constituent of the FTSE JPX Blossom Japan Sector Relative Index. The FTSE JPX Blossom Japan Sector Relative Index is used by a wide variety of market participants to create and assess responsible investment funds and other products. Morningstar, Inc., and/or one of its affiliated companies (individually and collectively, “Morningstar”) has authorized Hulic Co., Ltd to use of the Morningstar Japan ex-REIT Gender Diversity Tilt Logo (“Logo”) to reflect the fact that, for the designated ranking year, Hulic Co., Ltd ranks in the top quintile of companies comprising the Morningstar® Japan ex-REIT Gender Diversity Tilt IndexSM (“Index”) on the issue of gender diversity in the workplace. Morningstar is making the Logo available for use by Hulic Co., Ltd solely for informational purposes. Hulic Co., Ltd use of the Logo should not be construed as an endorsement by Morningstar of Hulic Co., Ltd or as a recommendation, offer or solicitation to purchase, sell or underwrite any security associated with Hulic Co., Ltd. The Index is designed to reflect gender diversity in the workplace in Japan, but Morningstar does not guarantee the accuracy, completeness or timeliness of the Index or any data included in it. Morningstar makes no express or implied warranties regarding the Index or the Logo, and expressly disclaim all warranties of merchantability or fitness for a particular purpose or use with respect to the Index, any data included in it or the Logo. Without limiting any of the foregoing, in no event shall Morningstar or any of its third-party content providers have any liability for any damages (whether direct or indirect), arising from any party’s use or reliance on the Index or the Logo, even if Morningstar is notified of the possibility of such damages. The Morningstar name, Index name and the Logo are the trademarks or services marks of Morningstar, Inc. Past performance is no guarantee of future results. Disclaimer This document contains forward-looking statements about performance of Hulic Co., Ltd. and its group companies based on the management assumptions made in light of currently available information. We do not post information for the purpose of soliciting investment. We request that investment decision be made at your own discretion and not by depending solely on the information provided in this material.